PMP Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Abig corporation with a large quantity of well-documented procedures is planning to acquire a small company. The potential loss of key resources due to uncertainty

around the merger is a significant concern.

What should the project manager do?


A.

Contract an external consulting firm to train new stakeholders in project management processes.


B.

Review the stakeholder matrix and evaluate needs for future projects.


C.

Create the risk register, evaluate the impact on projects, and share with the steering committee.


D.

Allocate project resources to assess the impacts on the actual projects in execution.