New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 18 Topic 2 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 18 Topic 2 Discussion

PMP Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?


A.

Organize a training for the new team member on the processes the team is currently using.


B.

Speak with the new team member at the retrospective and discuss potential improvements.


C.

Formalize the new processes and implement the team member's proposed changes.


D.

Hold a team meeting on governance, operating policies, procedures, and practices.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.