PMI Project Management Professional (2025 Version) PMP Question # 7 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 7 Topic 1 Discussion

PMP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?


A.

Business Documentation


B.

Stakeholder Register


C.

Risk Register


D.

Project Charter


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.