PMP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

A project team provided estimates for a hybrid project, but in every case those estimates were undervalued. On the current trajectory, the project will not meet its

intended value before it runs out of budget.

What should the project manager do?


A.

Review the number of sprints remaining and update estimates using planning poker.


B.

Convert the project to a pure agile approach and enforce sprint planning.


C.

Re-estimate the remaining project tasks and submit a change request.


D.

Monitor the budget variations to work with the governance process.