Questions # 51:

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

Options:

A.

Evaluate the project risk and add external experts to address the potential risks.


B.

Inform the project sponsor about the risk and try to convince them to withdraw from the project.


C.

Continue executing the project as planned and add more resources if they are required.


D.

Review the lessons learned on similar projects so that they do not fall back into the same pattern.


Expert Solution
Questions # 52:

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

Options:

A.

Work more closely with the agile team to eliminate the need for progress reports


B.

Record this in the issue log and find a resource to produce the reports


C.

Produce the progress reports on their own


D.

Engage a new resource to produce the progress reports


Expert Solution
Questions # 53:

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

Options:

A.

Strive toward continuous improvement


B.

Work together daily as a team


C.

Only share suggestions at the end of the sprint


D.

Follow the sprint planning


E.

Send communications to the entire team


Expert Solution
Questions # 54:

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.


B.

Review the communications management plan.


C.

Send the CEO one executive summary per week instead of five reports per week.


D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.


Expert Solution
Questions # 55:

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,


B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.


C.

Start executing the project as the scope will be defined and redefined throughout the project.


D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.


Expert Solution
Questions # 56:

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Options:

A.

Meet with each team member separately and apply an appropriate approach with each one.


B.

Approach the project sponsor and request help in discussing the project deliverables with team members.


C.

Explain to the team that the project manager is ultimately responsible for the delivery.


D.

Assign multiple managers to the various teams and delegate all of the tasks to them.


Expert Solution
Questions # 57:

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.

Confront the people causing the stress directly with the aim of finding amicable solutions


B.

Seek support from the project management office (PMO) on addressing issues affecting the project


C.

Discuss the possible actions with the project sponsor


D.

Avoid the people causing stress and request a transfer as soon as possible


E.

Talk to the human resources (HR) manager about these concerns


Expert Solution
Questions # 58:

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.


B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.


C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.


D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.


Expert Solution
Questions # 59:

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.


Expert Solution
Questions # 60:

A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.

What should the project manager do next?

Options:

A.

Engage with the functional manager to discuss details to obtain the required support.


B.

Request a teleconference meeting with the sponsor to submit a change request to allow the development team to conduct testing.


C.

Discuss testing requirements at the weekly project meeting to negotiate the best approach to test software.


D.

Send an email to the procurement specialist to negotiate with a company that specializes in software testing.


Expert Solution
Questions # 61:

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays


B.

Revise the project estimates and meet with the project team to discuss delays


C.

Review the management reserve to identify any costs associated with the delays


D.

Review the contingency reserve to identify any delays to the project


Expert Solution
Questions # 62:

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.


B.

Advise the project team on the importance of team engagement,


C.

Invest in coaching and training for all project team members.


D.

Escalate the issue with the human resource (HR) department to take action,


Expert Solution
Questions # 63:

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality


B.

Estimates


C.

Objectives


D.

Requirements


Expert Solution
Questions # 64:

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.


B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.


C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.


D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.


Expert Solution
Questions # 65:

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

Options:

A.

Require a written status report from all team members on a weekly basis


B.

Form a core group of team leads representing members from each country and encourage them to collaborate


C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day


D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately


Expert Solution
Questions # 66:

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

Options:

A.

Create a quality assurance plan for the documentation.


B.

Identify the components of the project documentation.


C.

Archive only the initial and draft versions of the documents.


D.

Ensure that the documents are in an easily retrievable form.


E.

Collect the documents at the time of their creation.


Expert Solution
Questions # 67:

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.

Review the benefits management plan


B.

Refer to the lessons learned from the first phase


C.

Consult the project reports from the previous project manager


D.

Collect information from related departments


Expert Solution
Questions # 68:

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

Options:

A.

Rolling wave planning and an adaptive approach


B.

Relative estimation to determine the task or deliverable sizes


C.

Iterations and reviews to continuously keep adapting the plan


D.

Bottom-up estimating based on a work breakdown structure (WBS)


E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects


Expert Solution
Questions # 69:

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes


B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously


C.

Stop the product release and start adding new user stones to the product backlog for any new requirements


D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration


Expert Solution
Questions # 70:

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion


B.

Conflict resolution


C.

Emotional intelligence


D.

Negotiating


Expert Solution
Questions # 71:

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline


B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change


C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline


D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline


Expert Solution
Questions # 72:

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities


B.

Conduct serial activities on tasks


C.

Increase the number of standup meetings


D.

Perform tasks in parallel


Expert Solution
Questions # 73:

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.


B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.


C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.


D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.


Expert Solution
Questions # 74:

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.


B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.


C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.


D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.


Expert Solution
Questions # 75:

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.


B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.


C.

Perform an independent analysis to determine the stakeholders from the client's organization.


D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.


Expert Solution
Questions # 76:

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

Options:

A.

Reassign the task to another member of the team


B.

Support the team member by providing one more resource to complete the task immediately


C.

Ask the team member if there is an impediment and help to remove the blockers


D.

Keep the project sponsor informed about the delay


Expert Solution
Questions # 77:

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager


B.

Arrange and conduct team-building sessions to improve team effectiveness


C.

Obtain feedback from the isolated team member to understand the situation


D.

Get feedback from other team members to understand what led to this situation


E.

Identify the isolated team member as a risk and document the situation in the risk register.


Expert Solution
Questions # 78:

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.

Allow the sponsor to determine how long the planning phase should last.


B.

Allow the client ta determine how long the planning phase should last.


C.

Ask the functional manager to work with the team to finalize planning and begin building the product.


D.

Explain that more features can be planned in upcoming Iterations and begin building the product.


Expert Solution
Questions # 79:

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.


B.

Seek approval from the sponsor on an extension of the project schedule,


C.

Seek approval from the quality board to skip the quality check.


D.

Ask the team member to work overtime to complete the quality check.


Expert Solution
Questions # 80:

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.


B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.


C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.


D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.


Expert Solution
Questions # 81:

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.


B.

Record the meeting to share with the team members who were unable to join.


C.

Ask the team members to use chat tools as an alternative to calls.


D.

Determine what the problem is and develop an action plan.


Expert Solution
Questions # 82:

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

Options:

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and cultural

observance information.


B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.


C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.


D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overall

project governance.


Expert Solution
Questions # 83:

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

Options:

A.

Review the integrated change control process to restrict the number of changes


B.

Focus on delivering incremental value through multiple smaller deliveries


C.

Request sponsor support to get buy-in from the users and stakeholders


D.

Restart the stakeholder engagement process by collecting user requirements again


Expert Solution
Questions # 84:

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change


B.

Ask the product owner to review the product backlog


C.

Ask the team members to analyze the impact of this change


D.

Ask the sponsor to approve the change request


E.

Ask the team members to include the change in the next iteration


Expert Solution
Questions # 85:

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

Options:

A.

Include stakeholders during daily standup meetings to monitor progress.


B.

Validate acceptance criteria with stakeholders prior to backlog refinement


C.

Avoid including stakeholders in iteration reviews.


D.

Create a requirements traceability matrix and distribute it accordingly


Expert Solution
Questions # 86:

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.


B.

Review the lessons learned from the previous project


C.

Identify the risk of implementing the new solution and evaluate the impact on the project.


D.

Create a lessons learned document for the initiation phase


Expert Solution
Questions # 87:

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions


B.

Inform management that commitments will not be met.


C.

Involve management to help resolve the conflicts


D.

Coach the team both as a whole and individually


Expert Solution
Questions # 88:

The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’

Options:

A.

Update the stakeholder engagement plan


B.

Review the latest project status report and update the stakeholders


C.

Escalate the case to the customer's management team


D.

Issue the project payment invoice to the customer in advance


Expert Solution
Questions # 89:

A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project

What should the project manager do first to determine a governance approach for the project?

Options:

A.

Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project


B.

Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines


C.

Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines


D.

Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project


Expert Solution
Questions # 90:

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

Options:

A.

A team member talking about a user story that is not on the Scrum board


B.

A team member talking about a user story that is on the Scrum board


C.

A technology that blocks agile capabilities


D.

A lack of team empowerment and an inability to self-organize


E.

A review of the backlog at daily standup meetings


Expert Solution
Questions # 91:

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.

Ensured the risk tolerance of the company was property updated


B.

Implemented the communications management plan properly


C.

Implemented the stakeholder engagement plan correctly.


D.

Provided a proper risk response


Expert Solution
Questions # 92:

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.

Ask the team member to enter this potential schedule delay in the risk register.


B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges


C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.


D.

Set up team-building activities with the project team members to reduce tension


Expert Solution
Questions # 93:

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.


B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly


C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties


D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer


Expert Solution
Questions # 94:

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

Options:

A.

Assign the tasks to another resource, and ask the resource to work double shifts


B.

Update the schedule to reflect the project's changes in duration


C.

Ask human resources (HR) for a replacement, and update the nsk register


D.

Update the resource management plan and resource allocation chart accordingly


Expert Solution
Questions # 95:

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

Options:

A.

Involved the business stakeholders in the sprint review


B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits


C.

Implemented a closing survey for key stakeholders


D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success


Expert Solution
Questions # 96:

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

Options:

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.


B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution


C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue


D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities


Expert Solution
Questions # 97:

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs


B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team


C.

The project manager should allow the resources to periodically choose on which team they would like to work.


D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization


Expert Solution
Questions # 98:

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

Options:

A.

Reviewed the communications management plan before inviting an external client representative to the meeting


B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting


C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register


D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting


Expert Solution
Questions # 99:

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.

Select a predictive development life cycle based on the team's experience


B.

Determine the most appropriate life cycle approach for the project


C.

Register all requirements into a backlog for further detailed analysis.


D.

Split the requirements, put them into two separate projects, and apply different approaches


Expert Solution
Questions # 100:

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

Options:

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.


B.

Check if the team member's activities are sufficiently documented to facilitate handover


C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected


D.

Reassign responsibilities across the remaining members using the available float for training.


E.

Obtain the project sponsors support to replace the team member on leave


Expert Solution