Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 6 out of 12 pages
Viewing questions 251-300 out of questions
Questions # 251:

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.


B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.


C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.


D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.


Expert Solution
Questions # 252:

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs


B.

Consult with team members and allow them to make a decision


C.

Convince the client not to make changes to the project


D.

Make transactional decisions focusing on the project goals


Expert Solution
Questions # 253:

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.


B.

Create a benefits management plan mapped to the organization's strategic objectives


C.

Perform a project cost-benefit analysis for the stakeholders


D.

Update the deliverables map against the agreed-upon project requirements


Expert Solution
Questions # 254:

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.

Propose a solution redesign for the project


B.

Perform risk analysis against the issue.


C.

Revise the project's quality control measurements


D.

Develop a mitigation based on the solution design


Expert Solution
Questions # 255:

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.


B.

Invite the project team to a swarming session to define a solution


C.

Leverage the network of the former department and ask for help


D.

Escalate the issue to the product owner to define the next steps


Expert Solution
Questions # 256:

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.


B.

Postpone the vacation to a different time.


C.

Ask the project sponsor to make any necessary decisions.


D.

Analyze the impacts and create a plan for team decision making


Expert Solution
Questions # 257:

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

Options:

A.

Seek help from the project sponsor to get an SME from another team in the organization.


B.

Provide an opportunity to one of the existing team members to become an SME.


C.

Hire a contractor from outside of the organization to continue with the project.


D.

Ask team members to document the issue and address it in the next project meeting.


Expert Solution
Questions # 258:

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments


B.

Incremental delivery and frequent backlog refinement based on user feedback


C.

Iterative development and collection of frequent feedback from project team members


D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented


Expert Solution
Questions # 259:

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.


B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.


C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.


D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.


Expert Solution
Questions # 260:

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

Options:

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.


B.

Set team performance goals and explain how the team receives the same performance scores.


C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.


D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.


Expert Solution
Questions # 261:

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project


B.

Analyze both projects to determine the most effective use of common resources


C.

Use resource optimization to justify requesting more resources for the critical project.


D.

Provide schedule optimization training to the project teams to improve their skills.


Expert Solution
Questions # 262:

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.


B.

Ensure that the priority of each task is clear to the team.


C.

Ask the team to self-organize and manage the work assigned.


D.

Tell the team which task to focus on at the next daily standup.


Expert Solution
Questions # 263:

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

Options:

A.

Start sending status updates to this stakeholder based on the request.


B.

Ask the stakeholder's manager if the stakeholder can be added to the list.


C.

Review the stakeholder engagement and communications management plans.


D.

Escalate the stakeholder’s request to the project sponsor.


Expert Solution
Questions # 264:

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

Options:

A.

Ask the project sponsor to replace the contractor since they do not have agile experience


B.

Issue a formal notice to the contractor to obtain an agile certification


C.

Consult the project team to understand the extent of the training needs for the contractor


D.

Instruct the contractor to receive agile training since the project has already started


Expert Solution
Questions # 265:

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.


Expert Solution
Questions # 266:

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

Options:

A.

Plan an outdoor activity tor the team to get to know each other


B.

Ask the team to review agile protect management approaches.


C.

Ask the human resources department for an experienced agile team


D.

Conduct a meeting to help the team define the team charter


Expert Solution
Questions # 267:

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.

Continue with the sprint as the progress shows buffers for potential interruptions.


B.

Ask the product owner if some low-priority stories could be cut from the sprint.


C.

Continue with the sprint work as planned and keep monitoring.


D.

Ask the project team to select any additional stories as they have additional capacity than planned.


Expert Solution
Questions # 268:

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)


B.

Statement of work (SOW)


C.

Scope management plan


D.

Memorandum of understanding (MOU)


Expert Solution
Questions # 269:

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.


B.

Include knowledge transfer sessions between the project and operations teams at every stage.


C.

Change the project management plan to add a final stage for product handoff to the operations team.


D.

Prepare detailed documentation to be shared with the operations team during project closure.


Expert Solution
Questions # 270:

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance


B.

Estimate the baseline impacts and submit a change request.


C.

Implement compression techniques to bring the project back on track.


D.

Review the resource management plan and organizational assets


Expert Solution
Questions # 271:

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

Options:

A.

Discuss with the product owner that the user story will not be completed this iteration.


B.

Meet with the team member's functional manager to try to remove the impediment.


C.

Tell the project team member not to work on the production issue and to inform their manager.


D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.


Expert Solution
Questions # 272:

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

Options:

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.


B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.


C.

Invite the PMO manager to the daily standup with the project team and product owner.


D.

Send weekly reports to all stakeholders, including the project team and the product owner.


Expert Solution
Questions # 273:

A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.

What should the project manager do?

Options:

A.

Ensure that people care about each other and work effectively together through effective team management.


B.

Meet with the team to discuss the correct, expected behavior in stressful situations and start practicing it.


C.

Establish a productive environment where all team members can assist one another with the workload.


D.

Create an environment of respect and fairness so the team can increase their project performance in stressful situations.


Expert Solution
Questions # 274:

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

Options:

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.


B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.


C.

Review the project approval requirements in the project charter and confirm who will be approving the project.


D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.


Expert Solution
Questions # 275:

A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

Options:

A.

Register a risk and escalate it to the project sponsor.


B.

Include the responsibility for acquisition with the core team.


C.

Detail the reason for the deliverable delay in the status report.


D.

Invite the stakeholders to discuss prioritization of a new deliverable.


Expert Solution
Questions # 276:

A project manager is leading a project team composed of members with varying levels of knowledge and

experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?

Options:

A.

Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.


B.

Ask each experienced member to be the mentor to one of the less-experienced members.


C.

Ask the more experienced members to review all of the tasks performed by the less-experienced members.


D.

Ask the resource manager to replace the less-experienced members with more experienced team members.


Expert Solution
Questions # 277:

Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.

How should the project manager impartially prioritize the requirements to be integrated?

Options:

A.

Retain only requirements that result in profitable revenue growth.


B.

Ensure the CEO selects the requirements from all department leaders.


C.

Give each department a fixed budget that will cover ten requirements.


D.

Rank the requirements with the highest benefit-cost ratio as more important.


Expert Solution
Questions # 278:

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

Options:

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.


B.

Assess the impact of the change and review the project management plan for next steps.


C.

Ask the financial manager to delay implementation due to potential project delays and penalties.


D.

Review the project schedule to determine which technique will reduce impact on project duration.


Expert Solution
Questions # 279:

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?

Options:

A.

Network diagram


B.

Decomposition


C.

Work breakdown structure (WBS)


D.

Resource leveling


Expert Solution
Questions # 280:

A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations


B.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk


C.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements


D.

Ask the general manager to review every requirement to ensure an projects will deliver the requested products


Expert Solution
Questions # 281:

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

Options:

A.

Business Documentation


B.

Stakeholder Register


C.

Risk Register


D.

Project Charter


Expert Solution
Questions # 282:

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager

do to get this information?

Options:

A.

Organize a one-on-one conversation with each stakeholder.


B.

Request stakeholders articulate their motivations at the kick-off meeting.


C.

Email project objectives to all stakeholders and ask for endorsement.


D.

Identify each stakeholder's motivations from the business case.


Expert Solution
Questions # 283:

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

Options:

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.


B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.


C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.


D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.


Expert Solution
Questions # 284:

As part of its growth strategy, management is providing all of its ongoing projects with junior employees and is requesting experienced team members to mentor them. The experienced employees argue that the mentoring program will not add value to their projects and will limit their ability to deliver.

How should the project manager handle this situation?

Options:

A.

Recommend to management that the junior employees should receive formal training and courses.


B.

Schedule time with all of the project team members since it is the role of the project manager to mentor the team.


C.

Allocate specific time for experienced team members to mentor the junior employees.


D.

Assign an instructor to mentor the junior employees so that the experienced team members can focus on project tasks.


Expert Solution
Questions # 285:

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

Options:

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.


B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.


C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.


D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.


Expert Solution
Questions # 286:

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not

shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

Options:

A.

Lack of team member training on documentation planning


B.

Improper assignment of tasks to team member pairings


C.

Incorrect communication techniques applied during implementation


D.

Team cohesiveness was lost because team members worked in pairs


Expert Solution
Questions # 287:

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

Options:

A.

Ensure that the schedule is aligned with the vision and objectives.


B.

Escalate the compliance issue to the project management office (PMO).


C.

Congratulate the team and move on to the execution phase.


D.

Develop a new detailed schedule with the team and project sponsor.


Expert Solution
Questions # 288:

Project team member A has a conflict with project team member B. The project manager believes project team member A's behavior is unacceptable. However, project team member A believes their behavior is appropriate.

What should the project manager do?

Options:

A.

Review the resource requirements to determine if the project team member is a good fit.


B.

Add an agenda item to the next team meeting to manage the conflict.


C.

Ask the project team member to review the team charter and follow up with a one-on-one meeting.


D.

Review the roles and responsibilities of each team member with the team.


Expert Solution
Questions # 289:

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

Options:

A.

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.


B.

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.


C.

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.


D.

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.


Expert Solution
Questions # 290:

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.

Provide the team with the enterprise environmental factors (EEFs).


B.

Run a benchmark with similar sites to compare compliance constraints.


C.

Look into lessons learned documentation for similar projects.


D.

Hire a specialized engineer to support the design team.


Expert Solution
Questions # 291:

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

Options:

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.


B.

Ask team members to research and collect data about the best features offered by similar products in the market.


C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.


D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.


Expert Solution
Questions # 292:

Construction work is preventing the project team members from entering the building where their offices are located.

What should the project manager do next?

Options:

A.

Inform the authorities so that they are aware of the situation and can take appropriate action.


B.

Continue business as usual since the construction work is not related to the project.


C.

Select the next action to be taken according to the risk management plan.


D.

Communicate with the stakeholders about the construction and ask for direction.


Expert Solution
Questions # 293:

A project manager works with a multifunctional team. During a review meeting, two team members disagree on the development approach.

What should the project manager do?

Options:

A.

Identify the best-fit approach and ask the team members to follow.


B.

Create goodwill among the team members for smooth operations.


C.

Review lessons learned and balance them within the team members' opinions.


D.

Consult the functional team manager for their guidance on best practices.


Expert Solution
Questions # 294:

The key stakeholders of a project would like to be actively involved in the review of product increments.

What should the project manager do?

Options:

A.

Analyze their interest and influence to manage expectations.


B.

Update the communications management plan for key stakeholders.


C.

Identify the needs and expectations of key stakeholders.


D.

Encourage their participation in release and sprint reviews.


Expert Solution
Questions # 295:

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.

The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?

Options:

A.

Risk management plan


B.

Quality management plan


C.

Communications management plan


D.

Procurement management plan


Expert Solution
Questions # 296:

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

Options:

A.

Contact the human resources (HR) department to find new resources to replace this critical resource.


B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.


C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.


D.

Discuss the resource management plan with the project team for effective utilization of critical resources.


Expert Solution
Questions # 297:

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?

Options:

A.

Meet with the new project sponsor to review the current project scope and the requested changes.


B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.


C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.


D.

Inform the new project sponsor that the new aspects will not be included in this project.


Expert Solution
Questions # 298:

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

Options:

A.

Assessed feasibility and impacts


B.

Developed benchmarking


C.

Analyzed stakeholders


D.

Detailed the project charter


Expert Solution
Questions # 299:

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

Options:

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.


B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.


C.

Contact the project sponsor to let them know you require more resources to meet the schedule.


D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.


Expert Solution
Questions # 300:

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

Options:

A.

Notify the stakeholder that arbitration procedures will be followed.


B.

Inform the project sponsor of the stakeholder's dissatisfaction.


C.

Document the issue in the issue log and send a report to management.


D.

Review the requirements traceability matrix and conduct inspections.


Expert Solution
Viewing page 6 out of 12 pages
Viewing questions 251-300 out of questions