Questions # 401:

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.


B.

Allow the project team to decide what is the most appropriate requirement to follow.


C.

Escalate to the project management office (PMO) and request a solution for the requirements.


D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.


Expert Solution
Questions # 402:

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

Options:

A.

Use the existing budget for executing the fallback plan and update the baseline.


B.

Add additional resources to the project to fast track certain activities and reduce delays.


C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.


D.

Communicate the delay to stakeholders and maintain the existing budget baseline.


Expert Solution
Questions # 403:

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.


B.

The project is under budget and on schedule.


C.

The project is under budget and behind schedule.


D.

The project is on budget and on schedule.


Expert Solution
Questions # 404:

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.

The product owner does not have visibility into what the team has done in the product increment.


B.

The product owner trusts the team and is marking the product as complete.


C.

The product owner has evaluated the product against the definition of done (DoD).


D.

The product owner will release the product to customers without showing them a demo.


Expert Solution
Questions # 405:

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

Options:

A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.


B.

Specify the scope and features to be deployed in the contract clearly.


C.

Work very closely with the customer and third parties to meet their needs.


D.

Change the marketing and product management definitions to meet stakeholder needs.


Expert Solution
Questions # 406:

A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project

manager notices that one team is consistently behind schedule and their work often needs to be corrected.

What should the project manager do to improve the quality of this team's work?

Options:

A.

Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.


B.

Review the issue with the project sponsor and work to reduce the scope for that team.


C.

Guide all team members and bring in external consultants to complete the work.


D.

Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.


Expert Solution
Questions # 407:

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.

Update the project management plan and adjust the project budget with this change request.


B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.


C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.


D.

Request a meeting with the stakeholders and their team members to inform them about this change.


Expert Solution
Questions # 408:

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.


B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.


C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.


D.

Create a record in the issue register and escalate the issue to the project steering committee.


Expert Solution
Questions # 409:

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.


Expert Solution
Questions # 410:

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

Options:

A.

Assign a development team member to have the responsibility of managing dependencies.


B.

Suggest that each project develops a high-level plan to monitor the dependencies


C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies


D.

Continue the project with 2-week iterations as dependencies will be managed individually


Expert Solution
Questions # 411:

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.

Add a fixed number of change requests allowed by the client on the project baseline.


B.

Request sponsor approval for all change requests to reduce the number of changes.


C.

Initiate the number of iterations to reduce the number of change requests.


D.

Reduce the number of approvers required to implement a change request.


Expert Solution
Questions # 412:

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.


B.

Provide team members with specific and clear instructions on the project objectives and tasks.


C.

Communicate the project's impact and plans to engage the project team throughout the project.


D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.


Expert Solution
Questions # 413:

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.


B.

Add more iterative techniques to improve stakeholder learning.


C.

Identify all the critical stakeholders during the project initiation.


D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.


Expert Solution
Questions # 414:

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.


B.

Escalate the issue to the product owner.


C.

Consult the communications management plan.


D.

Review the stakeholder register.


Expert Solution
Questions # 415:

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

Options:

A.

Assess the impact of the stakeholder and engage properly.


B.

Escalate the stakeholder issue to the project sponsor.


C.

Develop a specific communications strategy for this stakeholder.


D.

Use interpersonal skills to gain stakeholder engagement.


Expert Solution
Questions # 416:

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Ask the team member to resolve the issue independently to minimize further delays.


B.

Ask the team member to provide details to address the issue with the vendor.


C.

Implement fast tracking to reduce the impact of the delay on the sprint.


D.

Update the communications management plan to prevent future reoccurrence.


Expert Solution
Questions # 417:

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

Options:

A.

Set up a meeting with the team to discuss and determine the project's challenges.


B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.


C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.


D.

Meet with the data suppliers to explain the critical timing requirements of the project.


Expert Solution
Questions # 418:

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.

Request the team to work more for on-time delivery.


B.

Request the team to focus on doing better planning.


C.

Request the replacement of certain team members.


D.

Request management for a high-performing team.


Expert Solution
Questions # 419:

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.


B.

Examine ways of modifying the scope of the project.


C.

Adopt a resource leveling procedure to level the resources.


D.

Perform an impact analysis to see the effect on the project.


Expert Solution
Questions # 420:

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.


Expert Solution
Questions # 421:

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.


B.

Obtain management approval prior to implementing the new risk response.


C.

Use the management reserve to mitigate the risk.


D.

Implement the new response to address the risk.


Expert Solution
Questions # 422:

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.


B.

Use a kanban board to increase accountability.


C.

Use a product backlog to manage changes.


D.

Use a burnup chart to provide transparency.


Expert Solution
Questions # 423:

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.


B.

Archive the survey responses with project artifacts for future projects.


C.

Use the information to restart the project.


D.

Evaluate the information collected on areas of improvement.


Expert Solution
Questions # 424:

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

Options:

A.

Send out daily emails with the project status and task lists to all team members.


B.

Meet daily with the project team and include a monthly report on the risks and issues.


C.

Distribute a project newsletter that includes any project changes and required project information.


D.

Encourage collaboration on a daily basis, facilitating different communication channels.


Expert Solution
Questions # 425:

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.


B.

Add testing items to the backlog to assess quality periodically.


C.

Expand the team in order to improve the quality of the project.


D.

Compare the cost of improving quality against the cost of failure and adjust the budget.


Expert Solution
Questions # 426:

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

Options:

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.


B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.


C.

Communicate the latest status to the steering committee and provide a demo of the features completed.


D.

Schedule routine demos on features completed and deliver a single product once all features are completed.


Expert Solution
Questions # 427:

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

Options:

A.

Seek help from experts to support the team member in fixing the problem.


B.

Facilitate a session to reach an agreement with the team as a whole.


C.

Negotiate with the customer a delay in the project delivery.


D.

Accept the team's request to reassign the team member.


Expert Solution
Questions # 428:

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.

Escalate the issue to the engineer's functional manager.


B.

Discuss the issue with the engineer and determine how to prevent another problem.


C.

Document the task on the kanban board and make it the highest priority.


D.

Assign another engineer to the task due to the urgency.


Expert Solution
Questions # 429:

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

Options:

A.

Monitor all stakeholders.


B.

Keep all stakeholders informed.


C.

Analyze the stakeholders.


D.

Engage the stakeholders.


Expert Solution
Questions # 430:

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,


B.

Send emails with information about the project deliverables on the first day of the project.


C.

Connect with every location and check their preferred methods of communication.


D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.


Expert Solution
Questions # 431:

During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager

notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.

How should the project manager handle this situation?

Options:

A.

Set up a proper governance structure to ensure functional managers’ requests are processed correctly.


B.

Modify the communications management plan to enable functional managers to add changes to the project.


C.

Follow the project constraints and move forward with the agreed schedule baseline and the cost baseline.


D.

Ask the functional managers to communicate with their peers and emphasize the impact of their requirements.


Expert Solution
Questions # 432:

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

Options:

A.

Anticipate, alert, and follow the risk management process.


B.

Detect, track, and follow the issue management process.


C.

Promote, inspire, and follow the stakeholder engagement process.


D.

Discuss, educate, and follow the communications management process.


Expert Solution
Questions # 433:

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources


B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted


C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline


D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements


Expert Solution
Questions # 434:

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.


B.

Utilize the cloud wiki to collect the necessary knowledge.


C.

Coordinate with the team and the project stakeholders to collect the knowledge.


D.

Provide just-in-time knowledge to the client, upon request.


Expert Solution
Questions # 435:

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Options:

A.

Meet with the functional managers to align the expected frequency and results reporting for the team members.


B.

Provide performance feedback to the learn members' functional managers at the end of the year.


C.

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.


D.

Request to be made responsible for the performance plans of those on this project team


Expert Solution
Questions # 436:

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

Options:

A.

Start executing the project since leadership is responsible for the business strategy.


B.

Meet with the project sponsor to better understand the strategic benefits of the project.


C.

Propose an updated business case and project charter that are more aligned with the business strategy.


D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.


Expert Solution
Questions # 437:

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Schedule the meeting at the end of the day to accommodate everyone.


B.

Ignore the situation since the team member is accomplishing their deliverables.


C.

Reinforce the ground rules for standup meetings with the entire team.


D.

Speak with the team member directly to reinforce the ground rules.


Expert Solution
Questions # 438:

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored


B.

Provide an answer via email recommending a division of tasks between both roles.


C.

Politely inform the program manager that attending these meetings is no longer required.


D.

Schedule a meeting to discuss the different perspectives and agree on a decision.


Expert Solution
Questions # 439:

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.


B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.


C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.


D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.


Expert Solution
Questions # 440:

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.


B.

Evaluate and decide on a phased project management approach.


C.

Implement an adaptive project management approach.


D.

Use a hybrid model to combine predictive and adaptive life cycles.


Expert Solution
Questions # 441:

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

Options:

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.


B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex

items.


C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.


D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define

the project scope.


Expert Solution
Questions # 442:

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

Options:

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.


B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.


C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.


D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.


Expert Solution
Questions # 443:

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

Options:

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.


B.

Create a salience model to determine if the employee will have influence on the project.


C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.


D.

Assess the influence and power of the employee to see if the employee will add value.


Expert Solution
Questions # 444:

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.


B.

Coach the project owner about the implications of unplanned meetings.


C.

Discuss the issue with the project owner at the retrospective meeting.


D.

Escalate the situation to management because it is affecting the team.


Expert Solution
Questions # 445:

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

Options:

A.

Plan for continuous validation of the product.


B.

Discuss adding business scenario tests with the customer.


C.

Discuss adding additional test cases with the product owner.


D.

Add more test scenarios based on the issues found.


Expert Solution
Questions # 446:

A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big

of an expenditure for the company to undertake.

What should the project manager do in the future when working on new product projects?

Options:

A.

Make use of kanban boards so all stakeholders have a clear view of the project and provide their help accordingly.


B.

Increase the contingency reserve and prepare the team for applying fast-failing techniques when the estimates veer from the initial plan.


C.

Adopt a chain management approach, developing products based on the same platform and infrastructure.


D.

Train the team to first find the minimum viable product (MVP) that will deliver value to the customer.


Expert Solution
Questions # 447:

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.

Keep activities as planned regardless of the resource change.


B.

Update the burndown chart to reflect this resource's absence.


C.

Have a meeting with the resource to understand the issue.


D.

Request an additional resource to finish the project.


Expert Solution
Questions # 448:

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

Options:

A.

Update the communications matrix to ensure that client team member is included.


B.

Submit a change request to cover extra hours associated with project meetings.


C.

Increase the project meeting frequency and duration to allow for the extra work required.


D.

Speak with the client team member about the continuous delays during project meetings.


Expert Solution
Questions # 449:

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

Options:

A.

Prioritize the upgrade of project machines with the IT department.


B.

Inform the product owner and request more project resources.


C.

Schedule a session with stakeholders to understand the impact.


D.

Add product backlog items to prioritize operating system stories.


Expert Solution
Questions # 450:

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

Options:

A.

Move the task to the next sprint.


B.

Ask the team member to bring up the concern in the next daily meeting.


C.

Send an email explaining the issue to all team members.


D.

Reassign the task to another team member.