Questions # 501:

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assess

progress.


B.

Set up a feedback session with the product owner once a week so they can assess

progress.


C.

Instruct the team to refer the product owner to the project manager for information.


D.

Invite the product owner's functional manager to a feedback session to escalate the

issue.


Expert Solution
Questions # 502:

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

Options:

A.

Provide a software for instant messaging.


B.

Document all information on the team wiki.


C.

Promote the use of remote site syndication.


D.

Facilitate regular conference calls.


Expert Solution
Questions # 503:

A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?

Options:

A.

Identify and escalate any identified risks to the facilitator to handle


B.

Update the risk register during every iteration with any open concerns


C.

Use regular feedback loops through daily standups iteration demos and retrospectives


D.

Focus on developing a working deliverable instead of documenting risks


Expert Solution
Questions # 504:

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

Options:

A.

Implement a project newsletter so the different team members can be informed about

the progress of each project.


B.

Combine all of the small projects into one big project so the team can collaborate

better as one big team.


C.

Facilitate communication promoting a Scrum of Scrums so the different teams are

aware of the dependencies and progress.


D.

Make sure that each individual project schedule is aligned with the common deadlines.


Expert Solution
Questions # 505:

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

Options:

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive


B.

Remind the team frequently that the project must be delivered on time and within budget


C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork


D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues


Expert Solution
Questions # 506:

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

Options:

A.

Schedule crashing


B.

Fast tracking


C.

Earned schedule


D.

Earned value


Expert Solution
Questions # 507:

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.

Become a servant leader by supporting team collaboration and removing impediments


B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration


C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination


D.

introduce new communication tools to the project team members


Expert Solution
Questions # 508:

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

Options:

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.


B.

Review the historical information and make the decision based on the return on

investment (ROI).


C.

Ask the team to use company B's processes since they are more familiar with these

processes.


D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.


Expert Solution
Questions # 509:

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

Options:

A.

Request to meet with the team member and ask that any issues be escalated separately.


B.

Reprimand the team member and provide immediate coaching on goal alignment.


C.

Proceed with defining the goals with the team members given the majority approval from the team.


D.

Approach the team member with empathy and obtain agreement through collaboration.


Expert Solution
Questions # 510:

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Recognize the stakeholder's skills are important for the project and evaluate the

possibility of the stakeholder supporting the project team.


B.

Request the functional manager to assign the team from the lessons learned project to

the current project to avoid a learning curve.


C.

Ask the project team to review the lessons learned and have the team contact the

stakeholder directly if there are any questions.


D.

Send a request to the project sponsor to hire the stakeholder and have them become

part of the project team.


Expert Solution
Questions # 511:

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.

Evaluate the possibility of managing this project using a predictive approach.


B.

Submit a change request for a new team that has agile experience.


C.

Mentor the team to explain agile principles and create a shared understanding.


D.

Hire a functional manager who is familiar with agile methodologies.


Expert Solution
Questions # 512:

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives


B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders


C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project


D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable


Expert Solution
Questions # 513:

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field


B.

Team members, engineers, and weather experts


C.

Team members, consultants from outside the project with experience in the field, and the customer


D.

Weather experts, functional managers, and team members


Expert Solution
Questions # 514:

During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.

In order to reach a consensus and have a successful project completion, what should the

project manager do first?

Options:

A.

Analyze the bounds of the negotiation for agreement with both parties.


B.

Identify and satisfy both parties' underlying wants.


C.

Comply with the customer's request to achieve the project mandate.


D.

Initiate a change request to accommodate the revised cost of goods


Expert Solution
Questions # 515:

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Plan to execute the procurement tasks in a virtual environment.


B.

Review organizational process assets (OPAs) for similar projects.


C.

Create a change request to extend the duration of the project.


D.

Ask the project sponsor to put the project on hold.


Expert Solution
Questions # 516:

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives


B.

Subdivide the team to handle different aspects of the project


C.

Support the team to find and execute the minimum viable product (MVP)


D.

Organize project execution to satisfy the project sponsor s request


Expert Solution
Questions # 517:

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company's historical organizational project artifacts


B.

Company's project responsibility assignment matrix (RAM)


C.

Company's resource management plan


D.

Company's resource calendars


Expert Solution
Questions # 518:

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

Options:

A.

Meet with the stakeholder to discuss the impact of the deliverable


B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team


C.

Improve communication with the stakeholder to obtain their assistance in the future


D.

Escalate to the project sponsor due to the political nature of the issue


Expert Solution
Questions # 519:

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.

Negotiate the payments with the supplier and remind them of their long-term association


B.

Penalize the supplier according to the contract's service level agreement (SLA)


C.

Hire another information security supplier and incentivize them for speedy delivery


D.

inform the relevant stakeholders of this challenge and seek their support


Expert Solution
Questions # 520:

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

Options:

A.

Updated the stakeholder engagement plan to reflect a change in the product owner


B.

Communicated the status of the project more frequently with the product owner


C.

Updated the communications management plan to reflect a change in the communication needs


D.

Reevaluated the new product owner's needs for better engagement


Expert Solution
Questions # 521:

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

Options:

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.


B.

Organize a formal session led by a skilled facilitator with defined rules for how

participants will interact with one another.


C.

Distribute a questionnaire on the key features of the product and encourage the teams

to respond with their design recommendations.


D.

Hold multiple sessions of manageable sizes with participants from both teams to

discuss their ideas.


Expert Solution
Questions # 522:

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

Options:

A.

Advise the marketing director to receive formal training.


B.

Ask the marketing team members to coach their director.


C.

Train the marketing team and keep their director informed.


D.

Mentor the marketing director on the approaches.


Expert Solution
Questions # 523:

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.


B.

Find a way to maintain the project schedule.


C.

Impose authority on the project.


D.

Request additional resources from the sponsor and motivate the team.


Expert Solution
Questions # 524:

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.


B.

Check social media to determine if there are any common connections that use the new supplier.


C.

Request assistance from the procurement department on the next steps.


D.

Become aware of any cultural characteristics of the new supplier that could impact

negotiation.


Expert Solution
Questions # 525:

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new team

members.


B.

Set up a weekly meeting with the new team members for a couple of months.


C.

Request the transfer of the new members to another project, citing a risk of confusion.


D.

Update and share the guideline document dealing with team communication.


Expert Solution
Questions # 526:

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?

Options:

A.

Liaise with the functional managers to replace the team member.


B.

Engage with the team member and draw up a development plan.


C.

Organize quarterly team-building events.


D.

Request that a new team member be added to the team


Expert Solution
Questions # 527:

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Options:

A.

Reinforce the value of documenting and approving all change requests and ask the

customer to issue these through the agreed channels.


B.

Organize a meeting to mediate the relationship between the customer and the team

member to ensure no feelings are hurt.


C.

Ask the customer to email all requests directly to you and you will ensure they are

actioned by the correct team member.


D.

Explain to the customer that the team member was just trying to help and the changes

can be reverted if necessary.


Expert Solution
Questions # 528:

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices


B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant


C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)


D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting


Expert Solution
Questions # 529:

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.


B.

Discuss the issue with the functional manager to understand the reason for the

complaint.


C.

Support the team member and provide documentation to the functional manager

proving their performance.


D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.


Expert Solution
Questions # 530:

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

Options:

A.

Assessed the technical and organizational readiness for the project and identified risks

at the beginning of the first iteration


B.

Requested the product owner's approval to add an external expert to define the

acceptance criteria


C.

Defined a clear acceptance criteria at the initiation phase and continued with the

project


D.

Increased the communications between the team member and the product owner


Expert Solution
Questions # 531:

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.


B.

Ensure only the approved version is shared.


C.

Investigate how draft versions were shared.


D.

Ensure only the latest version is shared.


Expert Solution
Questions # 532:

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

Options:

A.

Ensure participation from all team members


B.

Ask the client to attend all daily calls.


C.

Ensure cross-departmental teams are colocated


D.

Request additional project resources


Expert Solution
Questions # 533:

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.


B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.


C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.


D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.


Expert Solution
Questions # 534:

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.


B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.


C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.


D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.


Expert Solution
Questions # 535:

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.


B.

Remove the project team member from all future meetings.


C.

Talk to the client privately to highlight the situation.


D.

Recommend a performance improvement plan to the project team member.


Expert Solution
Questions # 536:

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

Options:

A.

Add the situation to the project risk register to be managed


B.

Identify competitors that are qualified to replace the current supplier


C.

Inform the purchasing department that manages the supplier relationship


D.

Use the issue log to record the situation immediately


Expert Solution
Questions # 537:

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.

Held a touchpoint with marketing before the demo to discuss any impediments


B.

Scheduled a demo presentation of the product during the first reason


C.

Asked the marketing team to start working on the product immediately


D.

Confirmed marketing requirements and constraints when adding to the backlog


Expert Solution
Questions # 538:

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

Options:

A.

US$650,000


B.

US$452,500


C.

US$547,500


D.

US$582,500


Expert Solution
Questions # 539:

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Options:

A.

Perform an impact analysis with subject matter experts (SMEs).


B.

Inform the government representative about the impact of the separate project.


C.

Implement a change request to increase the budget and schedule.


D.

Consult and update the risk register with the project stakeholders.


Expert Solution
Questions # 540:

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

Options:

A.

Review the stakeholder engagement assessment matrix to determine next steps.


B.

Set up some time with the stakeholders to explain the importance of compliance.


C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.


D.

Send out documentation to align stakeholder expectations and project objectives.


Expert Solution
Questions # 541:

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

Options:

A.

Notify all team members that all steps in the process must be completed.


B.

Escalate the issue to the other executive leadership members.


C.

Schedule a review of the process steps with the team and the COO.


D.

Redesign the process so the team can move more quickly.


Expert Solution
Questions # 542:

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

Options:

A.

Evaluate the project exit criteria in the project charter.


B.

Reach out to the senior executive sponsor for the project.


C.

Understand the project success criteria and objectives.


D.

Review the project status reporting for the latest information.


Expert Solution
Questions # 543:

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.

Speak with the team member about their engagement and contributions


B.

Perform an assessment of each member of the project team


C.

Assign the team member to a team where they can contribute more


D.

Conduct a team building event to involve the team member


Expert Solution
Questions # 544:

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

Options:

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.


B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.


C.

Demand that the business team stop wasting time and define final requirements for the product.


D.

Tell the business team and Scrum team to continue following the initial plan.


Expert Solution
Questions # 545:

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

Options:

A.

Request a change in the contract to include the shipment in the project management

plan.


B.

Find the root cause of the issue and discuss the customer's current engagement.


C.

Inform the customer that subsequent packages cannot be manufactured.


D.

Request a delivery date extension from the customer


Expert Solution
Questions # 546:

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Options:

A.

Injury or loss incidents could delay project deliverables.


B.

It is imperative that established performance metrics are met.


C.

The project manager is obligated to comply with the project location's regulatory

requirements.


D.

The project manager must follow their employer's organizational process assets

(OPAs).


Expert Solution
Questions # 547:

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.


B.

Consult the risk management plan.


C.

Escalate the issue to the project management office (PMO).


D.

Refer the stakeholder to the project sponsor.


Expert Solution
Questions # 548:

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

Options:

A.

Regression analysis


B.

Stakeholder analysis


C.

Qualitative risk analysis


D.

Decision tree analysis


Expert Solution
Questions # 549:

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

Options:

A.

Ask the internal sales team to keep the customer informed of the delivered value


B.

Evaluate various delivery options in order to immediately demonstrate value to the customer


C.

Inform the customer about the progress and update them on the final deliverables


D.

Wait for an important milestone to complete and then inform the customer of the progress


Expert Solution
Questions # 550:

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.

Perform stakeholder engagement with the virtual team


B.

Add status reports to the communications management plan


C.

Convene an on-site meeting for both of the teams


D.

Add status report creation as a product backlog item