Question #: 512
Topic #: 52

During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?


A.

Log this as an issue in the issue log and address it with the project sponsor.


B.

Ignore the stakeholder as the product is almost complete.


C.

Explain that the needs will be updated in the stakeholder engagement plan.


D.

Inform the stakeholder that changes can happen in this project.