PMI Project Management Professional (2025 Version) PMP Question # 511 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 511 Topic 52 Discussion

PMP Exam Topic 52 Question 511 Discussion:
Question #: 511
Topic #: 52

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?


A.

Evaluate the possibility of managing this project using a predictive approach.


B.

Submit a change request for a new team that has agile experience.


C.

Mentor the team to explain agile principles and create a shared understanding.


D.

Hire a functional manager who is familiar with agile methodologies.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.