Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 511 Topic 52 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 511 Topic 52 Discussion

PMP Exam Topic 52 Question 511 Discussion:
Question #: 511
Topic #: 52

A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?


A.

Use a work breakdown structure (WBS) with firm start and end dates for all phases to ensure nothing is missed.


B.

Use a kanban board as an information radiator to manage work in progress (WIP) at the individual and organizational levels.


C.

Use a minimum viable product (MVP) to test and discover which features to schedule when and what to fail early.


D.

Use a product backlog of the functionalities and features required to provide the expected business benefit.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.