Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 511 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 511 Topic 52 Discussion

PMP Exam Topic 52 Question 511 Discussion:
Question #: 511
Topic #: 52

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?


A.

Review the project scope statement


B.

Confirm ownership for ongoing value realization


C.

Escalate the issue to the project sponsor


D.

Appraise the stakeholders of value gain progress


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.