PMI Project Management Professional (2025 Version) PMP Question # 510 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 510 Topic 52 Discussion

PMP Exam Topic 52 Question 510 Discussion:
Question #: 510
Topic #: 52

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?


A.

Recognize the stakeholder's skills are important for the project and evaluate the

possibility of the stakeholder supporting the project team.


B.

Request the functional manager to assign the team from the lessons learned project to

the current project to avoid a learning curve.


C.

Ask the project team to review the lessons learned and have the team contact the

stakeholder directly if there are any questions.


D.

Send a request to the project sponsor to hire the stakeholder and have them become

part of the project team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.