PMI Project Management Professional (2025 Version) PMP Question # 513 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 513 Topic 52 Discussion

PMP Exam Topic 52 Question 513 Discussion:
Question #: 513
Topic #: 52

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?


A.

Functional managers, team members, and external consultants with experience in the field


B.

Team members, engineers, and weather experts


C.

Team members, consultants from outside the project with experience in the field, and the customer


D.

Weather experts, functional managers, and team members


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.