PMI Project Management Professional (2025 Version) PMP Question # 514 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 514 Topic 52 Discussion

PMP Exam Topic 52 Question 514 Discussion:
Question #: 514
Topic #: 52

During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.

In order to reach a consensus and have a successful project completion, what should the

project manager do first?


A.

Analyze the bounds of the negotiation for agreement with both parties.


B.

Identify and satisfy both parties' underlying wants.


C.

Comply with the customer's request to achieve the project mandate.


D.

Initiate a change request to accommodate the revised cost of goods


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.