PMP Exam Topic 52 Question 515 Discussion:
Question #: 515
Topic #: 52

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?


A.

Organize a training for the new team member on the processes the team is currently using.


B.

Speak with the new team member at the retrospective and discuss potential improvements.


C.

Formalize the new processes and implement the team member's proposed changes.


D.

Hold a team meeting on governance, operating policies, procedures, and practices.