Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 516 Topic 52 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 516 Topic 52 Discussion

PMP Exam Topic 52 Question 516 Discussion:
Question #: 516
Topic #: 52

A project team working on a big data project has concluded the make-or-buy decision on a particular feature, which will drive an increase in product adoption. The team decided to buy commercial software.

What should the project manager do next?


A.

Request a purchase order.


B.

Inform the project sponsor.


C.

Update the risk register.


D.

Finalize change control.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.