Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 516 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 516 Topic 52 Discussion

PMP Exam Topic 52 Question 516 Discussion:
Question #: 516
Topic #: 52

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?


A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.


B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.


C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.


D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.