There is a problem with a project because some features are not in compliance with
regulations. Some stakeholders do not believe compliance is a priority, while others disagree.
What should the project manager do?
Review the stakeholder engagement assessment matrix to determine next steps.
Set up some time with the stakeholders to explain the importance of compliance.
Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.
Send out documentation to align stakeholder expectations and project objectives.
Submit