Question #: 539
Topic #: 54

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?


A.

Perform an impact analysis with subject matter experts (SMEs).


B.

Inform the government representative about the impact of the separate project.


C.

Implement a change request to increase the budget and schedule.


D.

Consult and update the risk register with the project stakeholders.