Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 538 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 538 Topic 54 Discussion

PMP Exam Topic 54 Question 538 Discussion:
Question #: 538
Topic #: 54

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?


A.

Invite the client and product owner to all planning, review, and retrospective meetings.


B.

Accept the escalations and manage them so the working relationship with the client isnot impacted.


C.

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.


D.

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.