A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?


A.

Add the situation to the project risk register to be managed


B.

Identify competitors that are qualified to replace the current supplier


C.

Inform the purchasing department that manages the supplier relationship


D.

Use the issue log to record the situation immediately