Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 537 Topic 54 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 537 Topic 54 Discussion

PMP Exam Topic 54 Question 537 Discussion:
Question #: 537
Topic #: 54

To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?


A.

Have the product manager work with the scrum master to assign specialists to user stories to meet the requirement.


B.

Convert the story points on user stories to hours to provide estimates of the potential costs to the product manager.


C.

Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.


D.

Refine the definition of done (DoD) for user stories to ensure that part of the completion is a verification review of the code.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.