Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 537 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 537 Topic 54 Discussion

PMP Exam Topic 54 Question 537 Discussion:
Question #: 537
Topic #: 54

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?


A.

Work with the team to understand and solve the issues


B.

Provide testing training to all the project team members


C.

Increase the sprint duration so the testing can be completed


D.

Add a new resource with testing skills to the team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.