PMP Exam Topic 51 Question 507 Discussion:
Question #: 507
Topic #: 51

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?


A.

Become a servant leader by supporting team collaboration and removing impediments


B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration


C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination


D.

introduce new communication tools to the project team members