Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 508 Topic 51 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 508 Topic 51 Discussion

PMP Exam Topic 51 Question 508 Discussion:
Question #: 508
Topic #: 51

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?


A.

Execute the smaller estimated activities.


B.

Resize the story points.


C.

Negotiate the estimation so it gets smaller.


D.

Break down the larger activities into smaller ones.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.