Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 505 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 505 Topic 51 Discussion

PMP Exam Topic 51 Question 505 Discussion:
Question #: 505
Topic #: 51

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?


A.

Concentrate on the current project milestones.


B.

Update the project management plan for this new work.


C.

Develop a business case and submit it to the client.


D.

Make all the changes and then show the client the results.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.