Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 506 Topic 51 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 506 Topic 51 Discussion

PMP Exam Topic 51 Question 506 Discussion:
Question #: 506
Topic #: 51

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?


A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.


B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.


C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.


D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.