PMI Project Management Professional (2025 Version) PMP Question # 506 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 506 Topic 51 Discussion

PMP Exam Topic 51 Question 506 Discussion:
Question #: 506
Topic #: 51

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?


A.

Schedule crashing


B.

Fast tracking


C.

Earned schedule


D.

Earned value


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.