PMI Project Management Professional (2025 Version) PMP Question # 501 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 501 Topic 51 Discussion

PMP Exam Topic 51 Question 501 Discussion:
Question #: 501
Topic #: 51

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?


A.

Invite the product owner to attend daily standup meetings so they can assess

progress.


B.

Set up a feedback session with the product owner once a week so they can assess

progress.


C.

Instruct the team to refer the product owner to the project manager for information.


D.

Invite the product owner's functional manager to a feedback session to escalate the

issue.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.