Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 501 Topic 51 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 501 Topic 51 Discussion

PMP Exam Topic 51 Question 501 Discussion:
Question #: 501
Topic #: 51

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?


A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.


B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.


C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.


D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.