Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 502 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 502 Topic 51 Discussion

PMP Exam Topic 51 Question 502 Discussion:
Question #: 502
Topic #: 51

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?


A.

Consider cultural differences among stakeholders.


B.

Conduct an integration meeting among all stakeholders.


C.

Schedule communication training for management-level stakeholders.


D.

Understand how political aspects can affect the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.