Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 503 Topic 51 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 503 Topic 51 Discussion

PMP Exam Topic 51 Question 503 Discussion:
Question #: 503
Topic #: 51

A project team consists of several consultants from an external vendor. These consultants often change from month to month.

What should the project manager do to communicate the organizational values?


A.

Distribute the team charter to new team members.


B.

Host a question and answer (Q&A) session with the new team members.


C.

Schedule a collaborative team outing to strengthen team relationships.


D.

Review communications options with the vendor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.