PMI Project Management Professional (2025 Version) PMP Question # 503 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 503 Topic 51 Discussion

PMP Exam Topic 51 Question 503 Discussion:
Question #: 503
Topic #: 51

A company is initiating a project to decommission inefficient sales channels. Several stakeholders argue that one channel that indicates a downturn in generating value is still more efficient than some of the channels that are planned to remain.

What should the project manager do?


A.

Plan for incremental and iterative delivery based on feedback from the marketing and sales team.


B.

Review and update the success criteria to ensure that the channel is not decommissioned.


C.

Inform the stakeholders that the list of channels to be decommissioned was approved by the CEO.


D.

Escalate the objection to the steering committee and human resources (HR) as a personal intimidation incident.