PMI Project Management Professional (2025 Version) PMP Question # 503 Topic 51 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 503 Topic 51 Discussion

PMP Exam Topic 51 Question 503 Discussion:
Question #: 503
Topic #: 51

A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?


A.

Identify and escalate any identified risks to the facilitator to handle


B.

Update the risk register during every iteration with any open concerns


C.

Use regular feedback loops through daily standups iteration demos and retrospectives


D.

Focus on developing a working deliverable instead of documenting risks


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.