PMP Exam Topic 53 Question 522 Discussion:
Question #: 522
Topic #: 53

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?


A.

Escalate the issue to the change control board (CCB).


B.

Ask the project team to analyze the impact.


C.

Register the risk and document the contingency plan.


D.

Have the project team brainstorm alternatives.