PMP Exam Topic 53 Question 522 Discussion:
Question #: 522
Topic #: 53

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?


A.

Send a formal communication regarding the missed milestone


B.

Delay sending a formal communication until the project team catches up


C.

Ask for a meeting with the sponsor to decide whether to send the formal communication


D.

Forego the formal communication and have a conversation with the supervisor