Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 519 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 519 Topic 52 Discussion

PMP Exam Topic 52 Question 519 Discussion:
Question #: 519
Topic #: 52

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?


A.

Update the risk register in order to add the issue.


B.

Review the issue log regarding the concern


C.

Revise the benefits management plan


D.

Assess the repository to check for inconsistencies.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.