PMI Project Management Professional (2025 Version) PMP Question # 519 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 519 Topic 52 Discussion

PMP Exam Topic 52 Question 519 Discussion:
Question #: 519
Topic #: 52

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?


A.

Negotiate the payments with the supplier and remind them of their long-term association


B.

Penalize the supplier according to the contract's service level agreement (SLA)


C.

Hire another information security supplier and incentivize them for speedy delivery


D.

inform the relevant stakeholders of this challenge and seek their support


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.