Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 519 Topic 52 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 519 Topic 52 Discussion

PMP Exam Topic 52 Question 519 Discussion:
Question #: 519
Topic #: 52

A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.

What should the project lead do?


A.

Meet each team member during their work hours to ensure all questions are answered in a timely manner.


B.

Inform all team members that they are required to check for messages every few hours to ensure fast response times.


C.

During daily check-ins, compile questions, coordinate with all team members, and agree to meet.


D.

Escalate to the project sponsor and request to replace certain team members so the time zones are aligned.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.