PMP Exam Topic 53 Question 520 Discussion:
Question #: 520
Topic #: 53

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?


A.

Request for information


B.

Scope statement


C.

Issue log


D.

Risk register