PMP Exam Topic 53 Question 525 Discussion:
Question #: 525
Topic #: 53

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?


A.

Move the solution designer to another team.


B.

Review the process that resulted in this situation.


C.

Stop work until the design document is completed.


D.

Ask the team to document the design.