PMI Project Management Professional (2025 Version) PMP Question # 525 Topic 53 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 525 Topic 53 Discussion

PMP Exam Topic 53 Question 525 Discussion:
Question #: 525
Topic #: 53

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?


A.

Send an email update to existing team members about the addition of the new team

members.


B.

Set up a weekly meeting with the new team members for a couple of months.


C.

Request the transfer of the new members to another project, citing a risk of confusion.


D.

Update and share the guideline document dealing with team communication.