Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 524 Topic 53 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 524 Topic 53 Discussion

PMP Exam Topic 53 Question 524 Discussion:
Question #: 524
Topic #: 53

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?


A.

Meet with the vendors to evaluate the impact on the budget.


B.

Implement crashing to mitigate the impact on the budget.


C.

Review the organizational process assets (OPAs) as a reference.


D.

Request the release of management reserve for the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.