PMI Project Management Professional (2025 Version) PMP Question # 524 Topic 53 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 524 Topic 53 Discussion

PMP Exam Topic 53 Question 524 Discussion:
Question #: 524
Topic #: 53

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?


A.

Engage the services of an interpreter who understands the project domain.


B.

Check social media to determine if there are any common connections that use the new supplier.


C.

Request assistance from the procurement department on the next steps.


D.

Become aware of any cultural characteristics of the new supplier that could impact

negotiation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.