PMI Project Management Professional (2025 Version) PMP Question # 544 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 544 Topic 55 Discussion

PMP Exam Topic 55 Question 544 Discussion:
Question #: 544
Topic #: 55

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?


A.

Analyze the problem with both teams to figure out If pan of the work must be redone.


B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.


C.

Demand that the business team stop wasting time and define final requirements for the product.


D.

Tell the business team and Scrum team to continue following the initial plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.