Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 544 Topic 55 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 544 Topic 55 Discussion

PMP Exam Topic 55 Question 544 Discussion:
Question #: 544
Topic #: 55

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?


A.

Follow the change management process and work with procurement if needed


B.

Engage an arbitrator to resolve any conflict while handling the new requirement


C.

Add the change to the next sprint to meet the customer's needs


D.

Allocate resources to work on the new feature immediately to complete the request


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.