Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 544 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 544 Topic 55 Discussion

PMP Exam Topic 55 Question 544 Discussion:
Question #: 544
Topic #: 55

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?


A.

Escalate the issue to the sponsor and ask for stakeholder engagement


B.

Review the project business case and update it periodically


C.

Plan for strategic program management


D.

Implement a communications management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.