Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 526 Topic 53 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 526 Topic 53 Discussion

PMP Exam Topic 53 Question 526 Discussion:
Question #: 526
Topic #: 53

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?


A.

Established ground rules before the discussion had started.


B.

Asked stakeholders not to voice their opinions during the meeting.


C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.


D.

Reinforced that higher-level management has the decision power.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.