PMI Project Management Professional (2025 Version) PMP Question # 526 Topic 53 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 526 Topic 53 Discussion

PMP Exam Topic 53 Question 526 Discussion:
Question #: 526
Topic #: 53

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?


A.

Liaise with the functional managers to replace the team member.


B.

Engage with the team member and draw up a development plan.


C.

Organize quarterly team-building events.


D.

Request that a new team member be added to the team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.