Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 527 Topic 53 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 527 Topic 53 Discussion

PMP Exam Topic 53 Question 527 Discussion:
Question #: 527
Topic #: 53

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?


A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget


B.

Engaged with the project sponsor to ensure support for the project manager's decision


C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped


D.

Convinced the functional manager to stop the activities that will run beyond the budget


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.