PMI Project Management Professional (2025 Version) PMP Question # 531 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 531 Topic 54 Discussion

PMP Exam Topic 54 Question 531 Discussion:
Question #: 531
Topic #: 54

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?


A.

Revisit the communication process control.


B.

Ensure only the approved version is shared.


C.

Investigate how draft versions were shared.


D.

Ensure only the latest version is shared.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.