Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 531 Topic 54 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 531 Topic 54 Discussion

PMP Exam Topic 54 Question 531 Discussion:
Question #: 531
Topic #: 54

A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.

What should the project manager do first?


A.

Gather additional information and ask the team to perform a root cause analysis.


B.

Update the master schedule to reflect the reprioritized deliverables.


C.

Ask the team to work with the product owner to reprioritize the backlog.


D.

Request additional information and discuss the feasibility options and impacts with the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.