Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 531 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 531 Topic 54 Discussion

PMP Exam Topic 54 Question 531 Discussion:
Question #: 531
Topic #: 54

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?


A.

Review organizational process assets (OPAs) for clarity.


B.

Document lessons learned before closing.


C.

Consult the project charter for next steps.


D.

Confirm the definition of done (DoD) has been met.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.