Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 530 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 530 Topic 54 Discussion

PMP Exam Topic 54 Question 530 Discussion:
Question #: 530
Topic #: 54

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?


A.

Discuss the issue with the team to resolve the disagreement.


B.

Ensure that there is consensus among the project stakeholders.


C.

Discuss the issue during the next sprint planning meeting.


D.

Support the outcome of the architects’ agreement.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.