PMI Project Management Professional (2025 Version) PMP Question # 530 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 530 Topic 54 Discussion

PMP Exam Topic 54 Question 530 Discussion:
Question #: 530
Topic #: 54

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?


A.

Assessed the technical and organizational readiness for the project and identified risks

at the beginning of the first iteration


B.

Requested the product owner's approval to add an external expert to define the

acceptance criteria


C.

Defined a clear acceptance criteria at the initiation phase and continued with the

project


D.

Increased the communications between the team member and the product owner


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.