Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.
What should the project manager do?
A.
Assess the benefit of using new technology versus old technology.
B.
Hire project resources with experience using the new technology.
C.
Propose training for the project team in batches on the new technology.
D.
Request incentives for the team to use the new technology.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.