Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 534 Topic 54 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 534 Topic 54 Discussion

PMP Exam Topic 54 Question 534 Discussion:
Question #: 534
Topic #: 54

A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?


A.

Ask the least experienced team members to work as assistants to the more experienced team members so they can gain some project experience.


B.

Ask the project sponsor to replace the least experienced team members with more experienced ones.


C.

Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.


D.

Assign critical project tasks to the most experienced team members as they are the only ones with the knowledge.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.