PMI Project Management Professional (2025 Version) PMP Question # 534 Topic 54 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 534 Topic 54 Discussion

PMP Exam Topic 54 Question 534 Discussion:
Question #: 534
Topic #: 54

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?


A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.


B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.


C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.


D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.