Questions # 201:

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Follow the organization's process and deliverables for predictive projects, even if

they compromise the agility and performance of the project.


B.

Use the risk register to document all of the compliance vulnerabilities generated by

the project so that all decisions are well documented and approved by stakeholders.


C.

Meet with the project management office (PMO)/compliance entity to work on

process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.


D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.


Expert Solution
Questions # 202:

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.

Escalate the issue to the team's manager.


B.

Remove some of the team members.


C.

Review the roles and responsibilities document.


D.

Develop working agreements with the team.


Expert Solution
Questions # 203:

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

Options:

A.

Add the issue to the issue log and determine the corrective action.


B.

Create a fishbone diagram to determine the root cause for the misunderstanding.


C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.


D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.


Expert Solution
Questions # 204:

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.


B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.


C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.


D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction


Expert Solution
Questions # 205:

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement


B.

Confirm ownership for ongoing value realization


C.

Escalate the issue to the project sponsor


D.

Appraise the stakeholders of value gain progress


Expert Solution
Questions # 206:

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.


B.

Analyze the project schedule and look for alternatives.


C.

Perform crashing and/or fast tracking of the schedule.


D.

Meet the team member and try to plan a course of action together.


Expert Solution
Questions # 207:

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

Options:

A.

Include the requirement into the project and schedule it as soon as possible


B.

Inform the project sponsor about the situation and request assistance


C.

Evaluate the impact that the inclusion of this new requirement will have on project performance


D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope


Expert Solution
Questions # 208:

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

Options:

A.

Provided copies of the stakeholder engagement plan to all team members.


B.

Defined the roles and responsibilities of the team members.


C.

Updated the communications management plan.


D.

Established ground rules for the team


Expert Solution
Questions # 209:

Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)

Options:

A.

Host a special meeting to talk about what happened.


B.

Escalate the issue to human resources (HR).


C.

Review the lessons learned document with the team.


D.

Conduct a team-building workshop.


E.

Discuss this incident in the project review meeting.


Expert Solution
Questions # 210:

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.


B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.


C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements


D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project


Expert Solution
Questions # 211:

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.


B.

Discuss the problem with the team and decide how to do the work together.


C.

Verify team performance and ask for improvement during daily standup meetings.


D.

Recommend that the project sponsor increases the budget to bring new resources.


Expert Solution
Questions # 212:

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.


B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.


C.

Ask the project managers to report on their projects using a Kanban board format.


D.

Request the program managers to be more accurate when presenting status reports.


Expert Solution
Questions # 213:

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

Options:

A.

Escalate the issue to a higher authority.


B.

Suspend the two key team members immediately.


C.

Put the issue on the agenda for the next team meeting.


D.

Reassign one of the key team members to a different task.


Expert Solution
Questions # 214:

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.

High-level product backlog


B.

Key performance indicators (KPls)


C.

Product vision


D.

Schedule performance indexes (SPIs)


E.

Product roadmap


Expert Solution
Questions # 215:

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.


B.

The project is under budget and on schedule


C.

The project is aligned with the project charter


D.

The protect is aligned with the benefits management plan


Expert Solution
Questions # 216:

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

Options:

A.

Increase the sprint duration to allow the team more time


B.

Prioritize the contents of the backlog and remove some stories


C.

Create a change request to modify the gate review goals


D.

Use the standup meeting to assess impediments and problems


Expert Solution
Questions # 217:

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

Options:

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.


B.

Continue to work on the project until the stakeholders and management come to a decision.


C.

Socialize with the stakeholders to better understand their needs and reset expectations.


D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.


Expert Solution
Questions # 218:

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

Options:

A.

How the quality was managed


B.

How the acceptance criteria were met


C.

How the scope was managed


D.

How the stakeholders were managed


Expert Solution
Questions # 219:

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.


B.

Commit to a detailed global plan from the initiation phase.


C.

Get agreement from stakeholders on high-level deliverables and requirements.


D.

Request the project management office (PMO) to review the initial plan


Expert Solution
Questions # 220:

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.


B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.


C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.


D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.


Expert Solution
Questions # 221:

Drag the technical practices on the left to the scenario on the right.


Expert Solution
Questions # 222:

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.


B.

Set up information review sessions before reconvening another approval session.


C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.


D.

Obtain approval as fast as possible and close the meeting.


Expert Solution
Questions # 223:

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

Options:

A.

Send this change request to the change control board (CCB) for approval.


B.

Approve the request for the specialized training.


C.

Reject the request as it does not impact the project deliverables.


D.

Validate if the training is within scope and budget.


Expert Solution
Questions # 224:

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register


B.

Ask the client to help solve the problem


C.

Start procuring this material from another supplier.


D.

Engage the project team to look for alternatives to find a solution


Expert Solution
Questions # 225:

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

Options:

A.

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity


B.

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country


C.

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues


D.

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time


Expert Solution
Questions # 226:

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

Options:

A.

Assess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.


B.

Invite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.


C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.


D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.


Expert Solution
Questions # 227:

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

Options:

A.

Change the approach with the team.


B.

Meet with an agile coach to handle this issue.


C.

Analyze the level of the team's agile maturity.


D.

Support the team members' growth and development.


Expert Solution
Questions # 228:

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.

Determine a leadership style that is suitable for that location.


B.

Check if resources from headquarters can also be assigned to the project.


C.

Mentor the team members to perform project management.


D.

Assign a local resource to manage communication with the team.


Expert Solution
Questions # 229:

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

Options:

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.


B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.


C.

Study the technology to assist the team in decision-making if progress slows.


D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.


Expert Solution
Questions # 230:

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.


B.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer


C.

Ask the customer to simplify the feature so that it can be implemented in one iteration


D.

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations


Expert Solution
Questions # 231:

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.

Analyzed the sponsor's communication requirements.


B.

Confirmed that the portal is providing adequate information.


C.

Verified that the project team is following the communications management plan.


D.

Ensured the sponsor had the necessary skills to use the portal.


Expert Solution
Questions # 232:

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

Options:

A.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.


B.

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.


C.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).


D.

Inform the scrum master so that the change can be discussed directly with the stakeholder.


Expert Solution
Questions # 233:

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

Options:

A.

Follow the change management process and work with procurement if needed


B.

Engage an arbitrator to resolve any conflict while handling the new requirement


C.

Add the change to the next sprint to meet the customer's needs


D.

Allocate resources to work on the new feature immediately to complete the request


Expert Solution
Questions # 234:

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.

Concentrate on the current project milestones.


B.

Update the project management plan for this new work.


C.

Develop a business case and submit it to the client.


D.

Make all the changes and then show the client the results.


Expert Solution
Questions # 235:

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.

Monitor the interactions between the vendor and infrastructure manager going forward.


B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.


C.

Escalate the issue to the sponsor so appropriate action can be taken.


D.

Instruct the vendor to correct the problem without additional arguments.


Expert Solution
Questions # 236:

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.


B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.


C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.


D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.


Expert Solution
Questions # 237:

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

Options:

A.

Prepare performance value reports for the business on an ongoing basis.


B.

Include demonstrations of the built portion of the product at the end of every sprint.


C.

Prepare a project report for the stakeholders and distribute it weekly.


D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.


Expert Solution
Questions # 238:

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.


B.

Continue project execution using the current blueprints from the client.


C.

Escalate this issue to the project sponsor


D.

Consult with the client to determine if project execution should be continued.


Expert Solution
Questions # 239:

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?

Options:

A.

Request additional budget to recruit more developers.


B.

Lower the recruitment criteria.


C.

Log the issue in the issue log.


D.

Analyze the impact and inform the stakeholders.


Expert Solution
Questions # 240:

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.

Evaluate the impact to the users and create a plan to address it.


B.

Inform users about the new changes and ask for their collaboration.


C.

Ask all managers to collaborate implementing this change to users.


D.

Start implementing the change so that users will eventually get used to it.


Expert Solution
Questions # 241:

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts


B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project


C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps


D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor


Expert Solution
Questions # 242:

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.

Ask the individual who is hosting the event to use private communication methods.


B.

Set up a meeting with the distracted team member to discuss any issues


C.

Add a social events section to the charter to handle these situations


D.

Ask the individual who is hosting the event to mark it as private


Expert Solution
Questions # 243:

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.


B.

Update the project management plan and mark the milestone as completed.


C.

Ask the vendor to validate the agreement for any deviations.


D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.


Expert Solution
Questions # 244:

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

Options:

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.


B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.


C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.


D.

Change the meeting time to the working time zones of the stakeholders who are complaining.


Expert Solution
Questions # 245:

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement


B.

Accept the request because it came from the project sponsor


C.

Refuse the project sponsor's request because it is out of scope


D.

Validate the proposed change's impact on the project.


Expert Solution
Questions # 246:

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.

What should the project manager do first?

Options:

A.

Review the benefits of the proposed changes in relation to the business case.


B.

Assess the time overrun, and start implementation to avoid additional delays.


C.

Request a provisional budget increase to avoid any budget overruns.


D.

Motivate the team to avoid the frustration of working on a prolonged project.


Expert Solution
Questions # 247:

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.


B.

Refer the team members to the project charter to resolve the conflict.


C.

Issue a new change request to evaluate this situation and communicate the result.


D.

Document the facts explained by the team members in the issue log.


Expert Solution
Questions # 248:

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.


B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.


C.

Review lessons learned from previous projects and organizational process assets (OPAs).


D.

Determine the communication needs, environment, and tools to get the message across.


Expert Solution
Questions # 249:

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?

Options:

A.

Cost oriented


B.

Deliverable oriented


C.

Customer oriented


D.

Team oriented


Expert Solution
Questions # 250:

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity


B.

Implement a checkpoint in the iteration to verify if the team is on track


C.

Conduct a focused retrospective to help the team to discover the root cause


D.

Ask the team to have a lower commitment for the next iteration


Expert Solution