Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 4 out of 12 pages
Viewing questions 151-200 out of questions
Questions # 151:

A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.

What should the project manager do?

Options:

A.

Promote the higher performing team member to a higher position


B.

Request the high-performing team member to mentor the other team members


C.

Remind the high-performing team member to focus on shared rewards rather than individual rewards


D.

Reward the high-performing team member privately to avoid team disruption


Expert Solution
Questions # 152:

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

Options:

A.

Ensure the sprint size is appropriate for the iteration duration.


B.

Promote changing the iteration duration in order to commit as planned.


C.

Engage in recruiting a highly skilled resource to reinforce the skills.


D.

Consider using a reward system to encourage timely delivery


Expert Solution
Questions # 153:

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.


B.

Ensure that knowledge transfer activities are executed as planned


C.

Release the resources and plan for a project completion celebration.


D.

Hold a steering committee meeting to inform them of the project completion


Expert Solution
Questions # 154:

A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.

What should the project manager do?

Options:

A.

Wait for the team to identify and solve the problem independently.


B.

Move the team member to another task that is more skill appropriate


C.

Have a confidential discussion with the team member to identify the root cause


D.

Start a discussion with all team members to help resolve the issues


Expert Solution
Questions # 155:

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee


B.

Functional managers


C.

Board of directors


D.

Advisory team panel


E.

Chief executive officer


Expert Solution
Questions # 156:

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.

Award certificates of appreciation to encourage the team


B.

Inform the team about the delivery pressure from the project sponsor


C.

Send a formal notice to team members instructing them to maintain performance


D.

Hire a few temporary team members to help with the additional work.


Expert Solution
Questions # 157:

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site


B.

Review the contract requirements and ask for the applicable evidence for quality assurance


C.

Have the vendor issue the quality documentation prior to the next delivery.


D.

Call the vendor and have them verbally guarantee the quality of the next site delivery


Expert Solution
Questions # 158:

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?

Options:

A.

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.


B.

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly


C.

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making


D.

Review the adequacy of the project's governance and ensure that an appropriate structure is in place


Expert Solution
Questions # 159:

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

Options:

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results


B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.


C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.


D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away


Expert Solution
Questions # 160:

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

Options:

A.

Understand the context and interdependencies of the process from the team members and then define improvements


B.

Continue with the process as is. and wait until the next phase to suggest any improvements


C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework


D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.


Expert Solution
Questions # 161:

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

Options:

A.

Escalate to the management team to increase the timeline based on the complexity of the project


B.

Wait for the other project estimates before planning the schedule


C.

Prioritize and estimate the milestones for the high-level requirements based on historical data


D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan


Expert Solution
Questions # 162:

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).


B.

Amend the project budget to include MVP testing


C.

Submit a change request to the project sponsor for accelerated testing.


D.

Develop the product as per the schedule to perform integration and testing


Expert Solution
Questions # 163:

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification


B.

Promote the team member to product owner to leverage the new knowledge with the clients


C.

Provide an incentive to team members who begin using the new tool on this project.


D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team


Expert Solution
Questions # 164:

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?

Options:

A.

Add an entry in the risk log


B.

Implement the changes


C.

Review target benefits.


D.

Improve the team's velocity


Expert Solution
Questions # 165:

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

Options:

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project


B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,


C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable


D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits


Expert Solution
Questions # 166:

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments


B.

Revisit the scope management plan and note this as a risk


C.

Schedule a meeting with the product owner and finance team to agree on course corrections


D.

Continue developing based on the project management plan and address the issue post delivery


Expert Solution
Questions # 167:

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?

Options:

A.

Request a replacement resource


B.

Perform a cost-benefit analysis


C.

Implement risk responses


D.

Perform Integrated Change Control


Expert Solution
Questions # 168:

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log


B.

Project management plan


C.

Risk management plan


D.

Risk register


Expert Solution
Questions # 169:

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

Options:

A.

Establish daily standups to review project progress and track the completion of deliverables


B.

Allow the team members to catch up at their own pace


C.

Alert the business stakeholders immediately of the schedule delay.


D.

Discuss the risk of project delay and work priorities with the respective functional managers


E.

Work with the team to identify options to accelerate project delivery.


Expert Solution
Questions # 170:

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance


B.

Create a survey template to collect feedback from stakeholders to reach an agreement


C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.


D.

Leverage expert judgment to determine the requirements that should be considered


Expert Solution
Questions # 171:

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

Options:

A.

Review the set of responsibilities with the team member


B.

Avoid the team member to prevent further conflicts


C.

Escalate the situation to the project sponsor


D.

Review the personnel skill documents


Expert Solution
Questions # 172:

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

Options:

A.

Complexity and the cost of development


B.

Industry trends and the technical approach


C.

Cost of delaying some features against business value


D.

Reusing components from another product


E.

Length of time each feature has been on the backlog


Expert Solution
Questions # 173:

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?

Options:

A.

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date


B.

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable


C.

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.


D.

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation


Expert Solution
Questions # 174:

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation


B.

Ask the stakeholders about the priority of this regulation


C.

Ask the product owner to include the requirements in the product backlog


D.

Ask the security department for details about regulations


E.

Ask the team members to include the requirements in the next iteration


Expert Solution
Questions # 175:

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources


B.

Forward the request to the project management office (PMO) to amend the organizational process assets


C.

Ask the project sponsor to obtain approval for implementation of the new approach


D.

Analyze the requirements that will need to be addressed under the requested method


Expert Solution
Questions # 176:

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate


B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate


C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.


D.

Use soft skills to convince the project sponsor to approve the new budget estimate


Expert Solution
Questions # 177:

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

Options:

A.

Ask the team member to follow the approved communications management plan to communicate their issue


B.

Schedule a meeting with the concerned team member to review and update the issue log together


C.

Review the risk register with the team member to find the proper response action for this issue.


D.

Ask the team member to raise a change request to assess the issue in detail


Expert Solution
Questions # 178:

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.


B.

Consult with the project management office (PMO) for guidance on project artifacts.


C.

Archive the project artifacts on the project manager's local computer for future reference.


D.

Document the project sponsor's instructions as the archived project artifacts.


Expert Solution
Questions # 179:

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.

Contact the human resource (HR) department for a solution.


B.

Speak with the key team member to clarify the situation.


C.

Conduct a meeting with the team to deliberate on a decision.


D.

Suspend the team member until further notice.


Expert Solution
Questions # 180:

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).


B.

Request additional budget for contingency.


C.

Perform a risk identification process with the project team.


D.

Consult with the project stakeholders.


E.

Discuss the possible impacts with subject matter experts (SMEs).


Expert Solution
Questions # 181:

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor.


B.

Review the resources required for the tasks on the critical path.


C.

Review and update the risk management plan.


D.

Allocate resources to develop the competencies of the other team members


Expert Solution
Questions # 182:

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team


B.

External subject matter experts (SMEs) and the team


C.

Project sponsor and the team


D.

Project sponsor and the external SMEs


Expert Solution
Questions # 183:

A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.

How should the project manager handle this situation?

Options:

A.

Discuss the company culture with the supervisor to clarify expectations.


B.

Review the overall organizational culture of the company again.


C.

Request that the new supervisor be assigned to another project.


D.

Explain to the workers that they need to listen to the supervisor.


Expert Solution
Questions # 184:

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

Options:

A.

Prioritize project A over project B since A is an external project and B is an internal project.


B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.


C.

Engage the human resource manager to employ a machine learning expert for project A.


D.

Plan project A to start at the end of project B when the machine learning expert is available.


Expert Solution
Questions # 185:

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.


B.

Assign the new team member tasks so that the team member knows on what to focus.


C.

Approach the team member to identify any issues and then plan a resolution accordingly.


D.

Review the project with the team member to ensure the project scope is understood


Expert Solution
Questions # 186:

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.


B.

Organize frequent team building sessions and update the risk register.


C.

Meet with the project sponsor and propose a corrective action for the project.


D.

Encourage participation in decision making and empower the team.


Expert Solution
Questions # 187:

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

Options:

A.

Have the team members resolve the issue on their own.


B.

Highlight the impact of their behavior and motivate the team member to make improvements.


C.

Gather information and find the root cause of the problem.


D.

Document the escalated issue and address it at the end of the project.


Expert Solution
Questions # 188:

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

Options:

A.

Evaluate the project risk and try to replace the project with another one within the organization.


B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.


C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.


D.

Continue executing the project using the project manager's usual methods as all projects are unique.


Expert Solution
Questions # 189:

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.

Incorporated the change within the scope of the project


B.

Reviewed the quality inspections


C.

Complied with the customer specifications


D.

Documented the technical reviews with the new change


Expert Solution
Questions # 190:

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Options:

A.

Check with the team to learn what can be done, and consult an expert


B.

Ask the sponsor to close the project and pay the contracted penalty.


C.

Check that this information was documented correctly


D.

Meet with the sponsor to ask for their support


Expert Solution
Questions # 191:

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

Options:

A.

Negotiate payment after all project migration is completed


B.

Sign a single agreement for the whole project


C.

Use fixed-price increments as user stories are completed.


D.

Confirm payment after each project retrospective


Expert Solution
Questions # 192:

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review


B.

Confirmed documentation requirements with stakeholders


C.

Updated the project templates


D.

Implemented a new change control policy


Expert Solution
Questions # 193:

During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?

Options:

A.

Log this as an issue in the issue log and address it with the project sponsor.


B.

Ignore the stakeholder as the product is almost complete.


C.

Explain that the needs will be updated in the stakeholder engagement plan.


D.

Inform the stakeholder that changes can happen in this project.


Expert Solution
Questions # 194:

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

Options:

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.


B.

Submit a change request to the financial manager to increase the funding and continue as is.


C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.


D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.


Expert Solution
Questions # 195:

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

Options:

A.

Identify an alternative site.


B.

Update the issue log


C.

Issue a change request


D.

Update the risk register.


Expert Solution
Questions # 196:

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

Options:

A.

Cancel the meeting and create the risk register using the project documents.


B.

Continue the meeting and send the updated risk register to all stakeholders.


C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.


D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.


Expert Solution
Questions # 197:

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team


B.

Escalate the issue to the functional manager


C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training


D.

Perform the quantitative risk analysis for the team member.


Expert Solution
Questions # 198:

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team


B.

Empower the team members to remove obstacles and blockers


C.

Address and remove obstacles and blockers for the team


D.

Add blockers to the issue log and risk management plan


Expert Solution
Questions # 199:

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.


B.

Document the request and escalate to upper management to consider a modification of the project charter.


C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.


D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.


Expert Solution
Questions # 200:

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.


B.

Wait for a date when all required attendees can be available onsite.


C.

Run separate meetings to accommodate everyone's schedule.


D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.


Expert Solution
Viewing page 4 out of 12 pages
Viewing questions 151-200 out of questions