Questions # 351:

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

Options:

A.

Consult the risk response plan.


B.

Assign the tasks to another team member.


C.

Update the resource calendar.


D.

Issue a request to the change control board (CCB).


Expert Solution
Questions # 352:

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

Options:

A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.


B.

Ask the construction manager to meet with the two team members to resolve the situation.


C.

Provide the construction manager with instructions on how to resolve the situation.


D.

Discuss the team members' concern with the construction manager and seek solutions.


Expert Solution
Questions # 353:

A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.

What should the project manager do to avoid these situations?

Options:

A.

Review the risk management plan.


B.

Review the resource management plan.


C.

Review the communications management plan.


D.

Review the stakeholder engagement plan.


Expert Solution
Questions # 354:

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

Options:

A.

Develop a more comprehensive template for the definition of done (DoD).


B.

Increase the percentage allocated for testing each backlog item.


C.

Organize more frequent sprint reviews with a broader audience.


D.

Establish a quality assurance (QA) team separate from the development team.


Expert Solution
Questions # 355:

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.

Record that the delay is attributable to the client and request a meeting.


B.

Check the contractual terms about liquidated damages and reject if not applicable.


C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.


D.

Schedule a detailed analysis of the delays using cause and effect.


Expert Solution
Questions # 356:

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

Options:

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.


B.

Establish a pull communications method to access knowledge repositories and lessons learned.


C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.


D.

Establish a push communications method for the team to share knowledge and lessons learned.


Expert Solution
Questions # 357:

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.

Accept the client's observations and pay the penalties as per the project contract details.


B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.


C.

Inform the project director of the change and complete the project so as to not incur any penalties.


D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.


Expert Solution
Questions # 358:

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain.

What should the project manager do?

Options:

A.

Invite stakeholders to discuss project requirements prioritization.


B.

Register a risk and define a contingency plan to finish the project on time.


C.

Ask to include some business subject matter experts (SMEs) in the team.


D.

Assist the team in proposing a minimum viable product (MVP).


Expert Solution
Questions # 359:

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

Options:

A.

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.


B.

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.


C.

Submit a request for extra time and budget related to the dependencies and technical difficulties.


D.

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.


Expert Solution
Questions # 360:

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

Options:

A.

Mitigate the risks that are applicable to the current and following iterations.


B.

Focus on the project deliverables rather than the documented risks.


C.

Agree that any issue can be handled when it becomes a problem.


D.

Acknowledge that the risks will be handled in the corresponding iteration.


Expert Solution
Questions # 361:

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

Options:

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.


B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.


C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.


D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.


Expert Solution
Questions # 362:

A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and

efficiency of the risk management process.

What should the project manager use to accomplish this?

Options:

A.

Stakeholder register


B.

Brainstorming session


C.

Audit meeting


D.

Assumption log


Expert Solution
Questions # 363:

A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

Options:

A.

Invite the board member to the next daily standup.


B.

Invite the board member to the next sprint retrospective.


C.

Invite the board member to a separate demo.


D.

Invite the board member to the next sprint review.


Expert Solution
Questions # 364:

A project manager is leading a hybrid project funded by a time and materials (T&M) agreement. The project was completed, and the client

accepted the delivery of the product. One week later, the client asked the project manager to fix two defects they found in the product. The project

manager responded with an estimate of time and money and asked the client to confirm this. The client disagreed and insisted that the work

should be done for free because it is a defect in the product.

What should the project manager have done to prevent this?

Options:

A.

Trained client engineers to support the product after its delivery.


B.

Reviewed the project quality control plan with the client.


C.

Suggested a fixed-cost basis and included free bug fixes for 1 month.


D.

Planned how the delivered product will be supported after its delivery.


Expert Solution
Questions # 365:

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

Options:

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.


B.

Delay developing the indirect tax module until the tax regulation comes into effect.


C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.


D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.


Expert Solution
Questions # 366:

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.


B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.


C.

Update the communications management plan and encourage the teams to review it promptly and proactively.


D.

Create a status reporting template and share it with all team members before the day ends.


E.

Schedule daily meetings with each team to understand their progress and concerns in detail.


Expert Solution
Questions # 367:

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.


B.

Request help from the project sponsor to get support from the sales agents.


C.

Escalate the issue to senior management to gain team buy-in


D.

Explain the change benefits to the sales agents' manager to get their support.


Expert Solution
Questions # 368:

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.

Risk register information


B.

Higher-level activities completed


C.

Milestones status report


D.

Resource breakdown structure (RBS)


Expert Solution
Questions # 369:

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

Options:

A.

Allow collaboration to smooth out communication between team members.


B.

Add collaboration tools to the communications management plan.


C.

Escalate these communication challenges to the project sponsor.


D.

Organize a team meeting to resolve the communication challenges.


Expert Solution
Questions # 370:

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

Options:

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.


B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external

stakeholders.


C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.


D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the

government.


Expert Solution
Questions # 371:

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.


B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.


C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.


D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.


Expert Solution
Questions # 372:

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.


B.

Follow the functional manager's recommendation to implement only predictive tools in the project.


C.

Make the decision on which project approach to use that would best fit the project.


D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.


Expert Solution
Questions # 373:

During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

Options:

A.

Discuss this issue with the project sponsor to request additional funding to implement mitigation


B.

Hire a construction management consultant to develop a comprehensive site execution plan


C.

Prequalify contractors with proven track records to eliminate productivity concerns


D.

Add construction productivity to the risk register and develop a mitigation strategy for site execution


Expert Solution
Questions # 374:

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.


Expert Solution
Questions # 375:

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Options:

A.

Improve the videoconferencing system to provide better availability and quality in order to increase communication.


B.

Have team ambassadors from each location travel to the other in order to facilitate communication and minimize issues.


C.

Facilitate a meeting with both teams so that they can agree on the issues and propose solutions that work for both teams.


D.

Move working windows so that team members can have increased overlap for the handover of status and issues to their counterparts.


Expert Solution
Questions # 376:

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control


B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.


C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.


D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.


Expert Solution
Questions # 377:

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.


B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.


C.

Document the kick-off meeting and close out the planning phase after the meeting is held.


D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.


Expert Solution
Questions # 378:

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

Options:

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed


B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.


C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.


D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.


Expert Solution
Questions # 379:

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.


B.

Escalate to the team member's functional manager that the report was not submitted as requested.


C.

Instruct the team member to provide the report and document this in the performance review.


D.

Reassign the report to another team member to prepare and submit it as requested.


Expert Solution
Questions # 380:

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

Options:

A.

Prioritize which backlog activities should be kept.


B.

Work on the backlog activities with fewer story points.


C.

Ask for more resources to clear the backlog activities.


D.

Assign an owner for each backlog activity and track progress.


Expert Solution
Questions # 381:

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.


B.

Confirm with the team members that the functional manager is responsible for the delivery.


C.

Ask the product owner to clarify the roles and responsibilities of the project team.


D.

Inform the functional manager that task allocation is the responsibility of the product owner.


Expert Solution
Questions # 382:

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.


B.

Ignore the obstacle and present the partial solution to the customer


C.

Focus on generating business value despite the obstacle


D.

Make changes to reprioritize the backlog because of the obstacle.


Expert Solution
Questions # 383:

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.


B.

Review similar projects in the company.


C.

Set the project's purpose, mission, and vision.


D.

Carry out the product backlog creation.


Expert Solution
Questions # 384:

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.


B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.


C.

Send a detailed report to each steering committee member ahead of the meeting.


D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.


Expert Solution
Questions # 385:

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed


B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early


C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated


D.

In the initiation process, as it happens concurrently with the project contract and project charter creation


Expert Solution
Questions # 386:

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

Options:

A.

The organizational process assets (OPAs) have been updated.


B.

The contractual deliverables of the project have been accepted.


C.

It The handover and deliverable acceptance have been completed.


D.

The lessons learned sessions have been conducted.


Expert Solution
Questions # 387:

A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

Options:

A.

Update the risk management plan.


B.

Extend the timeline of the project.


C.

Check the organizational process assets (OPAs).


D.

Acquire knowledgeable resources.


Expert Solution
Questions # 388:

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?

Options:

A.

Inform the team not to accept any changes, as it involves significant rework.


B.

Request management to update the project requirements accordingly.


C.

Request an update of only new requirements, as other changes involve rework.


D.

Inform management that the agreed-upon scope cannot be changed.


Expert Solution
Questions # 389:

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

Options:

A.

Reschedule the project taking this new information into account.


B.

Refer to the project's resource management plan.


C.

Ask the project sponsor for external resources.


D.

Create a change request to be validated by the project sponsor.


Expert Solution
Questions # 390:

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

Options:

A.

Use interpersonal skills to expedite the issue.


B.

Send a gentle reminder to the technical service team.


C.

Update the issue log with the status and priority.


D.

Issue a formal warning to the technical service team.


Expert Solution
Questions # 391:

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.


B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.


C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.


D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.


Expert Solution
Questions # 392:

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

Options:

A.

Personas


B.

Power influence grid


C.

Power user grid


D.

Salience model


Expert Solution
Questions # 393:

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

Options:

A.

Traditional delivery, to ensure high quality and that the product meets market demands


B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product


C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration


D.

Incremental delivery, to ensure that mobile capability is released fast to the users


Expert Solution
Questions # 394:

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?

Options:

A.

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future


B.

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates


C.

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand


D.

Planned a training to follow the specific course to bring the two team members to the required experience level


Expert Solution
Questions # 395:

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.


B.

Identify the impediment and associated risks at the daily standup.


C.

Escalate the impediment and associated risks to the business sponsor.


D.

Identify the impediment during the retrospective


Expert Solution
Questions # 396:

A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even

though reports have been sent on a weekly basis.

What should the project manager do to ensure all stakeholders are receiving proper information about the project?

Options:

A.

Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.


B.

Create daily progress reports and send them to all stakeholders.


C.

Include stakeholders in the weekly status meetings with the team.


D.

Assess all of the project stakeholders and document their preferred communication method and frequency.


Expert Solution
Questions # 397:

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team


B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment


C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment


D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting


Expert Solution
Questions # 398:

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.


B.

Add a risk to the risk register.


C.

Add it to the issue log as an ongoing issue.


D.

Review and validate the scope management plan.


Expert Solution
Questions # 399:

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

Options:

A.

Create better plans to test the functionality in more detail.


B.

Review the definition of done (DoD) with the product owner.


C.

Include previous sprint defects and close them in the actual sprint.


D.

Get approval from the product owner on the user stories.


Expert Solution
Questions # 400:

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

Options:

A.

Escalate the team member's disruptive behavior to their functional manager.


B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.


C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.


D.

Request team members document their decisions independently and share with each other.