Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 550 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 550 Topic 56 Discussion

PMP Exam Topic 56 Question 550 Discussion:
Question #: 550
Topic #: 56

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?


A.

Work with the product owner to evaluate and prioritize the requirements


B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list


C.

Determine the expected benefits of each requirement to maximize the overall business value


D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.