PMI Project Management Professional (2025 Version) PMP Question # 550 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 550 Topic 56 Discussion

PMP Exam Topic 56 Question 550 Discussion:
Question #: 550
Topic #: 56

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?


A.

Perform stakeholder engagement with the virtual team


B.

Add status reports to the communications management plan


C.

Convene an on-site meeting for both of the teams


D.

Add status report creation as a product backlog item


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.