Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 549 Topic 55 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 549 Topic 55 Discussion

PMP Exam Topic 55 Question 549 Discussion:
Question #: 549
Topic #: 55

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?


A.

Fast tracking


B.

Resource leveling


C.

Critical chain method


D.

Schedule crashing


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.