Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 551 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 551 Topic 56 Discussion

PMP Exam Topic 56 Question 551 Discussion:
Question #: 551
Topic #: 56

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?


A.

Document the issues and extend the project delivery timeline.


B.

Convene the steering committee and inform them of the impact to the project.


C.

Prioritize the user stories with issues and have the team resolve them


D.

Update the project management plan and risk management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.