PMI Project Management Professional (2025 Version) PMP Question # 551 Topic 56 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 551 Topic 56 Discussion

PMP Exam Topic 56 Question 551 Discussion:
Question #: 551
Topic #: 56

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?


A.

Conduct a consensus-building session to decide how to approach the next set of work.


B.

Escalate the issue to the product owner for resolution.


C.

Add this conflict to the agenda for discussion at the next daily standup meeting.


D.

Conduct a planning session to decide how to approach the next set of work.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.