PMI Project Management Professional (2025 Version) PMP Question # 517 Topic 52 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 517 Topic 52 Discussion

PMP Exam Topic 52 Question 517 Discussion:
Question #: 517
Topic #: 52

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?


A.

Company's historical organizational project artifacts


B.

Company's project responsibility assignment matrix (RAM)


C.

Company's resource management plan


D.

Company's resource calendars


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.