Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 517 Topic 52 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 517 Topic 52 Discussion

PMP Exam Topic 52 Question 517 Discussion:
Question #: 517
Topic #: 52

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?


A.

Reviewed the risk register to identify a response plan for the audit


B.

Assigned a project team member to ensure all project documentation was updated


C.

Updated the project management plan regularly and had it securely shared with all stakeholders


D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.