A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
According to the PMBOK Guide, 6th Edition, Section 9.2.2.1, “Resource calendars specify the availability, capability, and skills of human resources and the availability of equipment and materials.” The project manager should consult the company’s resource calendars to determine the availability and suitability of the resources required for the new project. This will help the project manager to estimate the duration, cost, and risk of the project, as well as to plan the resource allocation and management. The other options are not as relevant or accurate as the resource calendars for this purpose. The company’s historical organizational project artifacts may provide some useful information, but they may not reflect the current situation or the specific needs of the new project. The company’s project responsibility assignment matrix (RAM) may show the roles and responsibilities of the project team members, but it may not indicate their availability or skills. The company’s resource management plan may describe the policies and procedures for managing resources, but it may not provide the details of the individual resources required for the new project. References:
PMBOK Guide, 6th Edition, PMI, 2017, pp. 336-337.
How to Measure Your Project Resource Requirements, MetaPM, 2024, accessed on February 24, 2024.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit