Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 517 Topic 52 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 517 Topic 52 Discussion

PMP Exam Topic 52 Question 517 Discussion:
Question #: 517
Topic #: 52

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?


A.

Asked the project sponsor to review the budget


B.

Updated the budget before moving to another stage of the project


C.

Added enough budget to cover all uncertainties


D.

Used past projects as a reference during budget estimations


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.