A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.

How should the project manager address this request?


A.

Determine the additional funding needed and seek the sponsor's guidance.


B.

Support value-based delivery that is aligned with the project objectives.


C.

Follow the project change control process to formalize the change.


D.

Estimate the additional funding needed and seek the client's approval.