PMI Certified Associate in Project Management (CAPM) CAPM Question # 340 Topic 35 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 340 Topic 35 Discussion

CAPM Exam Topic 35 Question 340 Discussion:
Question #: 340
Topic #: 35

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?


A.

Burndown chart


B.

Velocity chart


C.

Definition of ready (DoR)


D.

Definition of done (DoD)


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.