Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 1 out of 8 pages
Viewing questions 1-50 out of questions
Questions # 1:

A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?

Options:

A.

Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.


B.

Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.


C.

Mitigate the risk by requesting an alternative public authority to participate in the approval process.


D.

Visit the public authority headquarters and formally petition them, demanding an explanation about the delay.


Expert Solution
Questions # 2:

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

Options:

A.

Expand the scope of the project.


B.

Schedule the tasks in sequence.


C.

Increase quality review cycles.


D.

Schedule the tasks in parallel.


Expert Solution
Questions # 3:

What earned value (EV) measure indicates the cost efficiency of the work completed?

Options:

A.

Cost variance (CV)


B.

Cost performance index (CPI)


C.

To-complete performance index (TCPI)


D.

Variance at completion (VAC)


Expert Solution
Questions # 4:

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)


B.

Estimate at completion (EAC)


C.

Earned value analysis (EVA)


D.

Budget at completion (BAG)


Expert Solution
Questions # 5:

Which two processes should be used to influence costs in the early stages of a project?

Options:

A.

Estimate Costs and Determine Budget


B.

Plan Cost Management and Estimate Activity Durations


C.

Control Quality and Control Costs


D.

Plan Stakeholder Engagement and Plan Communications Management


Expert Solution
Questions # 6:

Match the process with its corresponding Process Group:

Question # 6


Expert Solution
Questions # 7:

Which of the following is a group decision-making technique?

Options:

A.

Brainstorming


B.

Focus groups


C.

Affinity diagram


D.

Plurality


Expert Solution
Questions # 8:

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs


B.

Control Costs


C.

Plan Cost Management


D.

Determine Budget


Expert Solution
Questions # 9:

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders


B.

Project sponsor and project stakeholder


C.

Project manager and project team


D.

Project manager and project sponsor


Expert Solution
Questions # 10:

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs


B.

Estimate Activity Resources


C.

Control Costs


D.

Determine Budget


Expert Solution
Questions # 11:

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)


B.

Responsibility assignment matrix (RAM)


C.

Project assignment chart


D.

Personnel assignment matrix


Expert Solution
Questions # 12:

Administer Procurements is part of which Process Group?

Options:

A.

Planning


B.

Executing


C.

Monitoring and Controlling


D.

Closing


Expert Solution
Questions # 13:

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.


B.

Manage Project Team.


C.

Acquire Project Team.


D.

Plan Human Resource Management.


Expert Solution
Questions # 14:

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.


B.

project management plan.


C.

project scope statement.


D.

requirements management plan.


Expert Solution
Questions # 15:

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

Options:

A.

Learn methods


B.

collaborative teams


C.

Generalizing specialists


D.

Knowledge sharing


Expert Solution
Questions # 16:

Select three elements that apply to agile/ adaptive environments

Options:

A.

Frequent team checkpoints


B.

Colocation


C.

Access to information


D.

Virtual team members


E.

Geographically dispersed team


Expert Solution
Questions # 17:

An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

Options:

A.

Project Management Information System


B.

Project Management System


C.

Project Management Office


D.

Project Management Knowledge Area


Expert Solution
Questions # 18:

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests


B.

Performance reports


C.

Organizational process assets


D.

Project management plan


Expert Solution
Questions # 19:

Which contract type is least desirable to a vendor?

Options:

A.

Fixed price with economic price adjustment (FPEPA)


B.

Firm fixed price (FFP)


C.

Cost plus fixed fee (CPFF >


D.

Cost plus award fee (CPAF >


Expert Solution
Questions # 20:

What is the total float of the critical path?

Options:

A.

Can be any number


B.

Zero or positive


C.

Zero or negative


D.

Depends on the calendar


Expert Solution
Questions # 21:

Risk responses reflect an organization ' s perceived balance between:

Options:

A.

risk taking and risk avoidance.


B.

known risk and unknown risk.


C.

identified risk and analyzed risk.


D.

varying degrees of risk.


Expert Solution
Questions # 22:

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.


B.

there is no single way to manage a project.


C.

project management techniques are risk free.


D.

there is only one way to manage projects successfully.


Expert Solution
Questions # 23:

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks


B.

Perform Qualitative Risk Analysis


C.

Plan Risk Management


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 24:

What is the difference between verified and accepted deliverables?

Options:

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.


B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.


C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.


D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.


Expert Solution
Questions # 25:

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis


B.

Project charter


C.

Scope baseline


D.

Project scope statement


Expert Solution
Questions # 26:

Which of the following are outputs of define scope process in project scope management

Options:

A.

Requirements documentation and requirements traceability matrix


B.

Scope management plan and requirements management plan


C.

Project Scope statement and project documents updates


D.

Scope baseline and project documents updates


Expert Solution
Questions # 27:

What process is performed periodically throughout the project as needed?

Options:

A.

Plan Risk Management


B.

Plan Communications Management


C.

Plan Resource Management


D.

Plan Cost Management


Expert Solution
Questions # 28:

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Options:

A.

Close Project or Phase


B.

Conduct Procurements


C.

Control Procurements


D.

Close Procurements


Expert Solution
Questions # 29:

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes


B.

Resource limitations


C.

Risk analysis


D.

Quality audits


Expert Solution
Questions # 30:

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Options:

A.

Control chart


B.

Flowchart


C.

Checksheet


D.

Pareto diagram


Expert Solution
Questions # 31:

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.

Which of the following elements is the team using?

Options:

A.

Definition of ready (DoR)


B.

Burndown chart


C.

Backlog refinement


D.

Definition of done (DoD)


Expert Solution
Questions # 32:

What does leadership involve?

Options:

A.

Working with others through discussion or debate to guide them from one point to another


B.

Directing another person from one point to another using a known set of expected behaviors


C.

Working with a person using expert judgment to develop the technical deliverables


D.

Directing another person to develop the necessary expertise to establish technical deliverables


Expert Solution
Questions # 33:

Which role does the project manager resemble best?

Options:

A.

Orchestra conductor


B.

Facilities supervisor


C.

Functional manager


D.

School principal


Expert Solution
Questions # 34:

A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.

Which Scrum technique is this?

Options:

A.

Scaled Agile Framework (SAFe®)


B.

Disciplined Agile® (DA™)


C.

Large Scale Scrum (LeSS)


D.

Scrum of Scrums


Expert Solution
Questions # 35:

What is a tailoring consideration for Project Scope Management ' ?

Options:

A.

Life cycle approach


B.

Continuous improvement


C.

Validation and control


D.

Project complexity


Expert Solution
Questions # 36:

Which three of the following are key traits of a project leader? (Choose three)

Options:

A.

Rely on control.


B.

Focus on near-team goals.


C.

Convey trust and inspire trust in other team members.


D.

Challenge the status quo and do things differently.


E.

Focus on the horizon.


Expert Solution
Questions # 37:

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates


B.

Basis of estimates, cost estimates, project schedule, and risk register


C.

Business case, project charter, statement of work, and cost estimates


D.

Scope baseline, resource management plan, activity list, and assumption log


Expert Solution
Questions # 38:

What is the project manager ' s responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan


B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team


C.

Combining the results in all other knowledge areas, and overseeing the project as a whole


D.

Developing a strategy to ensure effective stakeholder communication


Expert Solution
Questions # 39:

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment


B.

Project management methodology


C.

Project management information system (PMIS)


D.

Project selection methods


Expert Solution
Questions # 40:

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Options:

A.

Histogram


B.

Quality audits


C.

Benchmarking


D.

Performance measurement analysis


Expert Solution
Questions # 41:

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

Options:

A.

Hold a face-to-face meeting with the project manager and warn them.


B.

Point the director to a link where they can take a look at the reports.


C.

Invite stakeholders to attend monthly progress review meetings.


D.

Ask the project manager to update the monthly status report distribution list.


Expert Solution
Questions # 42:

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

Options:

A.

Project activities


B.

Work packages


C.

Planning packages


D.

Project deliverables


Expert Solution
Questions # 43:

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control


B.

Direct and Manage Project Execution


C.

Close Project or Phase


D.

Monitor and Control Project Work


Expert Solution
Questions # 44:

Which are the most important competencies required for a project manager?

Options:

A.

Leadership, bilingualism, experience, and technical Knowledge


B.

PMP certification, experience, technical Knowledge, and post-graduate education


C.

Leadership, strategic and business management, project management knowledge, and technical knowledge


D.

Communication skills, project management knowledge, PMP certification, and availability to travel


Expert Solution
Questions # 45:

How does a requirements traceability matrix help to determine whether a product is ready for delivery?

Options:

A.

It captures assigned tasks and their estimated durations.


B.

It confirms the completion of all stories in the backlog.


C.

It assesses the quality of test cases and expected results.


D.

It tracks links between the approved requirements and each work product.


Expert Solution
Questions # 46:

The project management processes presented in the PMBOK Guide® should:

Options:

A.

always be applied uniformly.


B.

be selected as appropriate by the sponsor.


C.

be selected as appropriate by the project team.


D.

be applied based on ISO guidelines.


Expert Solution
Questions # 47:

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

Options:

A.

Analysis


B.

Appetite


C.

Tolerance


D.

Response


Expert Solution
Questions # 48:

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records


B.

project reports


C.

stakeholder notifications


D.

stakeholder register


Expert Solution
Questions # 49:

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

Options:

A.

The project manager should identify and deal with stakeholders only during the execution phase.


B.

Stakeholder satisfaction should be identified immediately and managed as a project objective.


C.

The project manager should focus on project objectives and deal with stakeholders as a secondary priority.


D.

Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.


Expert Solution
Questions # 50:

What key component of the project charter defines the conditions for dosing a project phase?

Options:

A.

Purpose


B.

Approval requirements


C.

Exit criteria


D.

High-level requirements


Expert Solution
Viewing page 1 out of 8 pages
Viewing questions 1-50 out of questions