Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 1 out of 8 pages
Viewing questions 1-50 out of questions
Questions # 1:

Which method should be used to elicit a cross-functional requirement?

Options:

A.

Focus groups


B.

Prototyping


C.

Facilitated workshops


D.

Interviews


Expert Solution
Questions # 2:

An adaptive project team is grooming the backlog for the next iteration. What does the team need to document in the user stories to determine the work needed to complete each story?

Options:

A.

Team velocity in past iterations


B.

Related epics of each story


C.

Product owner ' s priorities


D.

Detailed acceptance criteria


Expert Solution
Questions # 3:

Stakeholder satisfaction should be managed as a key project:

Options:

A.

Benefit


B.

Initiative


C.

Objective


D.

Process


Expert Solution
Questions # 4:

Agile release planning provides a high-level summary timeline of the release schedule based on.

Options:

A.

Activities and story points


B.

Iteration and prioritization plans


C.

Product roadmap and the product vision


D.

Tasks and user stories


Expert Solution
Questions # 5:

An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?

Options:

A.

Informal conversation


B.

Face-to-face meeting


C.

Short email update


D.

Written report


Expert Solution
Questions # 6:

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope


B.

Define Scope


C.

Plan Scope Management


D.

Collect Requirements


Expert Solution
Questions # 7:

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

Options:

A.

Project activities


B.

Work packages


C.

Planning packages


D.

Project deliverables


Expert Solution
Questions # 8:

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

Options:

A.

Project level


B.

Organizational level


C.

Industry level


D.

Influential level


Expert Solution
Questions # 9:

The process of identifying the stakeholders ' information needs is completed during:

Options:

A.

Plan Communications.


B.

Manage Stakeholder Expectations.


C.

Stakeholder Analysis.


D.

Identify Stakeholders.


Expert Solution
Questions # 10:

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

Options:

A.

Tornado diagrams and influence diagrams


B.

Detectability bubble charts and probability and impact matrix


C.

Hierarchical charts and burndown charts


D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts


Expert Solution
Questions # 11:

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

Options:

A.

Predictive


B.

Adaptive


C.

A mix


D.

Agile


Expert Solution
Questions # 12:

Which of the following are outputs of the Define Scope process in Project Scope Management?

Options:

A.

Requirements documentation and requirements traceability matrix


B.

Scope management plan and requirements management plan


C.

Project scope statement and project documents updates


D.

Scope baseline and project documents updates


Expert Solution
Questions # 13:

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

Options:

A.

Iterative


B.

On-demand


C.

Interactive


D.

Quality


Expert Solution
Questions # 14:

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Initiating


Expert Solution
Questions # 15:

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Options:

A.

Interactive


B.

Push


C.

Verbal


D.

Oral


Expert Solution
Questions # 16:

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.


B.

Tornado diagram.


C.

Pareto diagram.


D.

Ishikawa diagram.


Expert Solution
Questions # 17:

What is the process of ensuring that project resources are assigned and available?

Options:

A.

Control Procurements


B.

Acquire Resources


C.

Control Resources


D.

Plan Procurement Management


Expert Solution
Questions # 18:

Scope, schedule, and cost parameters are integrated in the:

Options:

A.

Performance measurement baseline.


B.

Analysis of project forecasts,


C.

Summary of changes approved in a period,


D.

Analysis of past performance.


Expert Solution
Questions # 19:

At the end of the project, what will be the value of SV?

Options:

A.

Positive


B.

Zero


C.

Negative


D.

Greater than one


Expert Solution
Questions # 20:

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?

Options:

A.

Encourage the team to follow the project plan that was developed with team input.


B.

Apply emotional intelligence (EI) skills, such as active listening, to understand the team ' s issues.


C.

Instruct the team members to self-organize and resolve any outstanding issues.


D.

Ask the team members to record their concerns in the lessons learned log for future action.


Expert Solution
Questions # 21:

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders


B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes


C.

Provides an actionable plan to interact effectively with stakeholders


D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders


Expert Solution
Questions # 22:

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement


B.

Cost performance baseline


C.

Benchmarking


D.

Cost of quality


Expert Solution
Questions # 23:

An issue log is an input to which Project Human Resource Management process?

Options:

A.

Manage Project Team


B.

Acquire Project Team


C.

Plan Human Resource Management


D.

Develop Project Team


Expert Solution
Questions # 24:

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.


B.

Historical information and the stakeholder register.


C.

Organizational process assets and the lessons-learned database.


D.

Project documents and historical information.


Expert Solution
Questions # 25:

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity


B.

Scatter


C.

Fishbone


D.

Matrix


Expert Solution
Questions # 26:

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Options:

A.

lead


B.

lag


C.

mandatory dependency


D.

internal dependency


Expert Solution
Questions # 27:

Which element does a project charter contain?

Options:

A.

Management reserves


B.

Work breakdown structure


C.

Stakeholder list


D.

Stakeholder register


Expert Solution
Questions # 28:

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Options:

A.

risk management plan


B.

human resource management plan


C.

scope management plan


D.

procurement management plan


Expert Solution
Questions # 29:

High-level project risks are included in which document?

Options:

A.

Business case


B.

Risk breakdown structure


C.

Project charter


D.

Risk register


Expert Solution
Questions # 30:

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution


B.

Stakeholder expectations and/or strategic opportunity (business need)


C.

Technological advancement and/or senior executive request


D.

Market demand and/or legal requirements


Expert Solution
Questions # 31:

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7


B.

8


C.

14


D.

16


Expert Solution
Questions # 32:

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure


B.

Staffing management plan


C.

Project organizational chart


D.

Scope management plan


Expert Solution
Questions # 33:

Which is an example of analogous estimating?

Options:

A.

Estimates are created by individuals or groups with specialized knowledge.


B.

Estimates are created by using information about resources of previous similar projects.


C.

Estimates are created by analyzing data.


D.

Estimates are created at the task level and aggregated upwards.


Expert Solution
Questions # 34:

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment


B.

Project management software


C.

Vendor bid analysis


D.

Reserve analysis


Expert Solution
Questions # 35:

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business


B.

Achieving the project objectives; providing management oversight for an administrative area


C.

A facet of the core business; achieving the project objectives


D.

Both are responsible for achieving the project objectives.


Expert Solution
Questions # 36:

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up


B.

Three-point


C.

Parametric


D.

Analogous


Expert Solution
Questions # 37:

Where are key project deliverables documented?

Options:

A.

Project management plan


B.

Requirements traceability matrix


C.

User acceptance criteria


D.

Work breakdown structure (WBS)


Expert Solution
Questions # 38:

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates


B.

Work performance information, change requests, project management plan updates, and project documents updates


C.

Communications management plan, project management plan updates, work performance report, and project documents update


D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates


Expert Solution
Questions # 39:

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

Options:

A.

Low-fidelity prototyping


B.

High-fidelity prototyping


C.

Data prototyping


D.

Report prototyping


Expert Solution
Questions # 40:

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?

Options:

A.

Develop consensus among stakeholders


B.

Get the budget approved for change


C.

Make sure management is aware of the change


D.

Get approval from the change control board


Expert Solution
Questions # 41:

Which document can help a project manager to leverage historical project information?

Options:

A.

Lessons learned register


B.

Schedule baseline


C.

Work performance data


D.

Deliverable acceptance forms


Expert Solution
Questions # 42:

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Options:

A.

updates.


B.

defect repairs.


C.

preventive actions.


D.

corrective actions.


Expert Solution
Questions # 43:

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

Options:

A.

create the project management plan.


B.

identify the project objectives.


C.

review and update stakeholder engagement.


D.

create the schedule baseline.


Expert Solution
Questions # 44:

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform


B.

Continuous


C.

Discrete


D.

Linear


Expert Solution
Questions # 45:

Which roles does the project manager resemble best?

Options:

A.

Orchestra conductor


B.

Facilities supervisor


C.

Functional manager


D.

School principal


Expert Solution
Questions # 46:

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

Options:

A.

2


B.

3


C.

4


D.

6


Expert Solution
Questions # 47:

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied


B.

Keep informed


C.

Manage closely


D.

Monitor


Expert Solution
Questions # 48:

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects


B.

Information technology software and employee capability


C.

Resource availability and employee capability


D.

Marketplace conditions and legal restrictions


Expert Solution
Questions # 49:

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.

Which process is the project manager executing?

Options:

A.

Manage Quality


B.

Plan Quality Management


C.

Control Quality


D.

Plan Scope Management


Expert Solution
Questions # 50:

Which process determines the risks that may affect the project and documents their characteristics?

Options:

A.

Control Risks


B.

Plan Risk Management


C.

Plan Risk Responses


D.

Identify Risks


Expert Solution
Viewing page 1 out of 8 pages
Viewing questions 1-50 out of questions