Question #: 1
Topic #: 1

A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?


A.

Discuss this with the department head and arrive at an acceptable solution to expedite the approval process.


B.

Report the issue to major stakeholders and explore possible corrective actions along with legal assistance.


C.

Mitigate the risk by requesting an alternative public authority to participate in the approval process.


D.

Visit the public authority headquarters and formally petition them, demanding an explanation about the delay.