PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

CAPM Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

In which of the Risk Management processes is the project charter used as an input?


A.

Plan Risk Responses


B.

Implement Risk Responses


C.

Plan Risk Management


D.

Perform Quantitative Risk Responses


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.