Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

CAPM Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

When can we say that a project is completed?


A.

When the planned time duration is completed


B.

When the project objectives have been reached


C.

When the project manager has left the team


D.

When the project team decides to stop the work on the project


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.