New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 133 Topic 14 Discussion

CAPM Exam Topic 14 Question 133 Discussion:
Question #: 133
Topic #: 14

At the end of the project, what will be the value of SV?


A.

Positive


B.

Zero


C.

Negative


D.

Greater than one


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.