Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 132 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 132 Topic 14 Discussion

CAPM Exam Topic 14 Question 132 Discussion:
Question #: 132
Topic #: 14

In adaptive projects, who should approve the prioritization of the backlog?


A.

Project manager


B.

Project sponsor


C.

Business analyst


D.

Product owner


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.